gvtcx

analysis

how long you wait after bidding

Half of UK public sector contracts are awarded within 19 days of the closing date, but one in ten takes more than 110. Measured across 330,518 contracts where the buyer published both a deadline and an award date — a wait no official source reports.

median wait
19 days
slowest tenth
over 110 days
contracts measured
330,518
what is being measured

The gap between the date bids closed and the date the buyer records as the award. It is the wait a bidder actually experiences after submitting, which is the thing nobody publishes — not a measure of how efficient a buyer is, and not a service standard anyone has committed to.

79,910 contracts (19.4% of those carrying both dates) record an award before their own closing date and are excluded. That is not a buyer awarding early: an award notice republishes the tender's original deadline, so an extended deadline, a re-published lot or a call-off against an older parent all produce one. They cannot say how long anything took.

how long it takes

waitcontracts
within a week 108,409
1 to 4 weeks 93,462
1 to 3 months 84,801
3 to 6 months 29,333
6 to 12 months 11,022
over a year 3,491

buyers that take longest

The 20 slowest by median, of the organisations with at least 100 measurable contracts. A long median is not necessarily poor administration — complex or high-value work takes longer to evaluate, and a body buying nothing but that will sit high here.

by category

Every category with at least 1,000 measurable contracts, slowest first.

how this was counted

From the tender closing date and the award date as published on notices across Contracts Finder, Find a Tender, Public Contracts Scotland and Sell2Wales. Counts are of contracting processes, not published notices: a tender and its award notice are one contract and are counted once, and where a contract has several awards the earliest award date is used.

411,726 contracts carry both dates. 79,910 record an award before their own closing date and are excluded, as are any gap beyond 730 days, leaving 330,518 measured here.

Medians throughout, never means: 3,491 contracts took more than a year, and an average would let them speak for the typical case. The distribution above is shown so the median is read with its spread rather than on its own.

The award date is the date the buyer records, which is not always the date a decision was taken — some publish the date the notice was filed. It is the only date the feeds carry, and it is what a bidder experiences.

Contains public sector information licensed under the Open Government Licence v3.0.