Manchester Airport Pier 2 Phase 2 - TP2300 Shell & Core
key details
| Value | £22,000,000 |
|---|---|
| Status | active |
| Category (CPV) | 45213330 +11 more |
| Region | North West |
| Deadline | 30 Aug 2022 |
| Procedure | selective |
| OCID | ocds-h6vhtk-03594c |
description
TP2300 Shell & Core
The scope of these works includes:
Design, manufacture/supply and install elements to construct Pier body onto pre-installed foundations as per MAG project team overall design.
Pier body to consist of: -
-Structural chassis consisting of elements placed on a recti-linear grid as defined in architectural layouts.
-Preassembled/premanufactured flooring systems
-Preassembled façade cassettes
-Preassembled roofing cassettes
-Premanufactured staircases
-Premanufactured lift shafts
-Premanufactured service risers
Pier body construction to utilise overall preassembly of elements e.g.
-Modular sections of structural chassis preassembled
-Installing premanufactured floor, façade, and roof sections directly onto preassembled modular assemblies
-Integration of other packages into preassembled modular assemblies e.g., MEP package 6300 – prefabricated plantrooms, Risers, Service modules etc The Pier will be constructed over a 17-month period from Q3, 2023 to Q4, 2024.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 5 Aug 2022 | Utilities contract notice (F05) | Earlier regulations | 021549-2022 |
more from MAG Airport PLC
- Manchester Airport Group Vertical Transportation Framework · £20,000,000 · 22 Aug 2022
- Manchester Airport Terminal 2 Reconfiguration - TP2800 Steelwork · £6,000,000 · 13 May 2022
- Manchester Airport Pier 2 Phase 2 Project DFMA · £60,000,000 · 13 May 2022
all contracts from this buyer →
source
Published on Find a Tender. Contact details for named individuals are not reproduced on this site.