613868 - A64 Bramham to H Bar Eastbound Resurfacing (Net Zero Concept Scheme)
key details
| Value | £906,222 |
|---|---|
| Status | complete |
| Category (CPV) | 45233210 |
| Region | Yorkshire and the Humber |
| Deadline | 5 Sept 2024 |
| Contract start | 6 Sept 2024 |
| Contract end | 1 Nov 2024 |
| Procedure | selective |
| SME suitable | Yes |
| OCID | ocds-b5fd17-fd97f911-84c8-4e9b-bce7-5f9e02b59759 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| Tarmac Trading | £906,222 | 4 Sept 2024 | active |
description
The Contractor is to form a collaborative team with other National Highways Suppliers to plan, prepare, construct and administer the work as detailed in this brief. Individual scope of work for each Supplier is detailed in "Additional Scope".
The Contractor:
| - | shall undertake the role of Principal Contractor for this project. |
| - | is responsible for planing out the existing carriageway surfacing and installing the new surfacing as detailed on the scheme drawings. |
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 20 Sept 2024 | Award (award) | · | d31cfc7a-fda8-4301-a9d8-16b07137e518-787208 |
more from National Highways
- PDF - Framework - A120 Horsley Cross - Parkeston Rbt Harwich Safety Impt · £28,022 · 28 Nov 2025
- PDF Framework - A27 Falmer Footbridge Headroom · £2,390 · 28 Nov 2025
- PDF Framework - RM1016 Holyport interchange · £11,909 · 28 Nov 2025
- PDF Framework - A5 EB WB M42 J10 - A5148 Wall SCRIM · £302,105 · 28 Nov 2025
- PDF Framework - A23 S Downs Way, Hickstead, Pyecombe Bundle - SDF Part 2 & 3 · £3,921,468 · 28 Nov 2025
- PDF Framework - A63 Brighton Street to Daltry Street Resurfacing · £555,028 · 28 Nov 2025
- PDF Framework - M6 J9 SB & NB Bescot Viaduct Pavement Hybrid Group 43 · £40,084 · 28 Nov 2025
- GI - BAM A38 signing · £43,972 · 28 Nov 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- PDF Framework - A38 NB Exit to Toyota Island Pavement · National Highways Limited · £182,463
- PDF Framework - A64 Grimston to Hopgrove Pavement · National Highways Limited · £552,596
- PDF Framework - A3 NB & SB Thursley-Hindhead Tunnel · National Highways Limited · £1,680,475
- PDF Framework - A14 J33 to J34 NRTS Ducted Network · National Highways Limited · £70,912
- Supply Chain Relationship · National Highways Limited · £1,683
- PDF Framework - A38 NB SB Weeford Island - Toyota Pavement · National Highways Limited · £530,778
- PDF framework - A500 Campbell Road - Waterproofing - Structures - Construction (Pavement) · National Highways Limited · £112,611
- PDF Framework - M5 J24-25 INCL J24 EXIT AND ENTRY SLIPS SB MP 195.0-203.0 RS · National Highways Limited · £3,341,673
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.