key details
| Value | £330,000 |
|---|---|
| Status | complete |
| Category (CPV) | 73220000 |
| Deadline | 8 Apr 2026 |
| Contract start | 2 Jul 2026 |
| Contract end | 31 Mar 2029 |
| Procedure | selective |
| SME suitable | Yes |
| OCID | ocds-b5fd17-991251a4-d597-4d92-b151-70771e9861fa |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| AtkinsRéalis Jacobs Joint Venture | £272,959 | 1 Jul 2026 | active |
description
Barton High Level Bridge (BHLB) is an eighteen-span steel-concrete composite structure carrying the M60 over the Manchester Ship Canal. The original bridge, constructed in 1960, comprised two independent deck halves formed from four longitudinal composite girders each, separated by a central reserve joint and supported by reinforced concrete bank seat abutments and hollow-column piers. The bridge was later widened between 1986 and 1989 as part of the M63 improvement works, with new edge girders and an extended deck slab added on both sides. Pre-widening investigations identified slight alkali-aggregate reactivity (AAR) in the original concrete, prompting a change in design approach. Instead of creating monolithic widened piers, the new outer supports were redesigned as independent, free-standing hollow reinforced-concrete columns founded on separate piles and connected to the original piers via link-and-pin "Pin Bearings". This configuration allowed independent vertical behaviour while constraining lateral and longitudinal movement, with the understanding that long-term monitoring and periodic bearing adjustments would be required to manage differential movements.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 3 Jul 2026 | Award (award) | · | 5749e1a2-e8e5-4723-952e-2e2b02c447dd-904624 |
more from National Highways Limited
- HRE - GCL/38 - Kirklee - Finnieston (Kelvin Bridge Branch) - Botanic Garden Station · £97,002 · 31 Jul 2026
- PDF Framework - A11 SBAttlebro-A1075 &NB A1075-FenSt rm&rsf Pk3.17 · £1,527,207 · 30 Jul 2026
- A47 J17-J20EB&J20-EyeGr rsf +J18-J19WBdrain Pk3.46 · £4,005,163 · 30 Jul 2026
- M5 J31-30 NB MP 258.6-256 RS · £769,492 · 30 Jul 2026
- PDF Framework - M61 Over Hulton to Chequerbent SDF · £1,674,453 · 30 Jul 2026
- ITEP0981 - Contract Management System · £3,450,000 · 30 Jul 2026
- ITEP0745 - M25 DBFO Contract - icloud · £29,118 · 29 Jul 2026
- Provision of temporary additional capability within the Information Rights function · £100,000 · 29 Jul 2026
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- JTP Improvement Programme · Suffolk Constabulary · £13,500
- S30119 Safety risk management continuous improvement · National Highways Limited · £72,976
- Strategic Advice for the Real Estate Vision Plan · Guy's and St Thomas' NHS Foundation Trust · £40,000
- Liverpool City Region Transport Model Update · Liverpool City Region Combined Authority · £1,200,000
- S30128 Asset delivery asset maintenance (GM701) & inspection (GS801) update · National Highways Limited · £184,967
- S30113 IS055001 Auditing Services · National Highways Limited · £178,546
- S30102 Third Party NSIPs Technical Partner · National Highways Limited · £2,500,000
- S30099 NHSS Review Implementation Phase 3 · National Highways Limited · £50,000
source