T0697 Structures Moonshot Phase 3a
key details
| Value | £450,000 |
|---|---|
| Status | complete |
| Category (CPV) | 73220000 |
| Deadline | 23 Jun 2025 |
| Contract start | 9 Jul 2025 |
| Contract end | 31 Mar 2026 |
| Procedure | selective |
| SME suitable | Yes |
| OCID | ocds-b5fd17-55e6f8f5-bdb0-4a91-b0ac-290713b4f08e |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| Atkins Jacobs Joint Venture | £448,455 | 8 Jul 2025 | active |
description
National Highways is aiming to make a step change in the use of technology for managing its structures assets. The underlying ambition of this initiative (known as 'Structures Moonshot') is to reduce human intervention on site, facilitate automated inspections/remote monitoring and facilitate decision making supported by artificial intelligence and machine learning. Initially, the focus for this work was post-tensioned concrete structures, which were recognised as requiring a greater level of scrutiny than most other structure types. As the project has developed the scope has been broadened to include other structures, particularly those categorised as 'Priority Risk' structures within the business, including structures with half-joints and structures with deck hinges. The objective is to facilitate the use of emerging technologies (used remotely where possible) to provide reliable condition data enabling better informed decisions and appropriate interventions at the optimum time.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 10 Jul 2025 | Award (award) | · | 40c499a5-f4a2-41db-8a91-e893f4e8f8a8-853912 |
more from National Highways
- PDF - Framework - A120 Horsley Cross - Parkeston Rbt Harwich Safety Impt · £28,022 · 28 Nov 2025
- PDF Framework - A27 Falmer Footbridge Headroom · £2,390 · 28 Nov 2025
- PDF Framework - RM1016 Holyport interchange · £11,909 · 28 Nov 2025
- PDF Framework - A5 EB WB M42 J10 - A5148 Wall SCRIM · £302,105 · 28 Nov 2025
- PDF Framework - A23 S Downs Way, Hickstead, Pyecombe Bundle - SDF Part 2 & 3 · £3,921,468 · 28 Nov 2025
- PDF Framework - A63 Brighton Street to Daltry Street Resurfacing · £555,028 · 28 Nov 2025
- PDF Framework - M6 J9 SB & NB Bescot Viaduct Pavement Hybrid Group 43 · £40,084 · 28 Nov 2025
- GI - BAM A38 signing · £43,972 · 28 Nov 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- S30149 LCOR maintenance, improvements and MCI advisory · National Highways Limited · £93,989
- S30138 TLOT10211 ATE Design Assurance Services Contract · National Highways Limited · £750,000
- S30125 Integrated Customer Function Development Technical Partnership · National Highways Limited · £36,500,000
- S30135 Impulse Geophysics Surveys · National Highways Limited · £579,989
- S30108 National Highways Growth and Housing Accelerator Fund Technical Support · National Highways Limited · £2,456,657
- S30129 Road Design DMRB Standards Research & Development CD127, CD109 & CD116 · National Highways Limited · £229,672
- S30141 Technical Standards Implementation, Governance improvements and benefit realisation · National Highways Limited · £402,000
- S30133 Multi-model Corridor investment study and Active Travel pipeline development · National Highways Limited · £225,000
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.