gvtcx

T0465 Drainage DMRB Review and Update

National Highways Published 5 Jul 2023 Contracts Finder
The value below is a framework or dynamic market ceiling: the maximum that could be spent across all call-offs, not the value of a single contract. Aggregate figures on this site exclude these to avoid double counting.

key details

Value£244,739
Statuscomplete
Category (CPV) 73220000
Deadline2 Jun 2023
Contract start5 Jul 2023
Contract end31 Oct 2024
Procedureselective
SME suitableYes
OCIDocds-b5fd17-245ab387-5b9f-4150-b70e-5e7d17f56771

Award

SupplierValueDateStatus
WSP UK Ltd £244,739 4 Jul 2023 active

description

National Highways "the Client" is seeking to set up a contract for the provision of technical service to undertake the review and update of the Design Manual for Roads and Bridges (DMRB) with Drainage content.

The DMRB review and update is required to align the DMRB with the new MCHW to ensure a complete set of technical and contract requirements. The DMRB update is required to incorporate the design requirements and guidance which currently sit within the current MCHW and address all areas where the new MCHW requires a design decision / input.

The updated DMRB documents will be required to demonstrate a clear and consistent flow through of requirements from the DMRB to the relevant MCHW clauses and/or Work Specific Requirements (WSRs).

Opportunities to deliver more efficient and effective practices in design, construction, maintenance and operations leading to reduced costs and better value need to be considered through considering challenges to the existing (and new) documents for alternative options.

Innovative SuDS designs are continually being developed, so these documents are to be reviewed to ensure that current best practice, as appropriate for the SRN, is reflected.

A new DMRB document for Chambers is required to carry content removed from the MCHW.

The documents produced and process followed (including accompanying governance documentation) will be subject to the National Highways' Manual for Development of Documents (MDD).

There are also a number of corrections, amendments and additions required to the suite of existing DMRB documents.

Drafting of the DMRB Drainage documents shall be completed and submitted to Technical Standards Committee (TSC) for consultation start no later than January 2024. TSC consultation shall be completed by August 2024 with final documents ready for publication.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
5 Jul 2023 Award (award) · 2da00c7d-2f80-4fd6-ab04-d8fbcb739877-659886

more from National Highways

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.