T0571 Delays from Roadworks metric - Development Stage Functions
key details
| Value | £141,476 |
|---|---|
| Status | complete |
| Category (CPV) | 73220000 |
| Deadline | 25 Apr 2024 |
| Contract start | 7 Jun 2024 |
| Contract end | 31 Mar 2025 |
| Procedure | selective |
| SME suitable | Yes |
| OCID | ocds-b5fd17-a4795001-397d-4f96-b219-88160bda1037 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| WSP UK Ltd - SPaTS 1 | £141,476 | 6 Jun 2024 | active |
description
National Highways are, via the Customer, Strategy and Communications Directorate Strategic Route Planning Team, required to produce route strategies as part of our operating licence and forms the initial evidentiary basis for the wider business in is preparation of future investment priorities as part of the RIS cycle. The strategies set our mid to long term needs for the network and identify where further investigation is needed to inform our investment programme.
For the current RIS cycle, 20 Route Strategy Initial Overview Reports (IORs) have been produced and published in PDF and ArcGIS StoryMap format in May 2023 using an approach that was agreed in 2021 with the executive board and Secretary of State.
The route strategies are to be refreshed to take account of feedback from the public, stakeholders following publication in May 2023, as well as some updated data sources and are planned for publication alongside the Strategic Business Plan in 2025 as final Route Strategies.
As part of the refresh there are a number of follow-on tasks that need to be completed that require a direct award to the current consultancy team to ensure consistency and value for money.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 7 Jun 2024 | Award (award) | · | e188988f-09c0-414a-93b3-75b3b457a74e-757574 |
more from National Highways
- PDF - Framework - A120 Horsley Cross - Parkeston Rbt Harwich Safety Impt · £28,022 · 28 Nov 2025
- PDF Framework - A27 Falmer Footbridge Headroom · £2,390 · 28 Nov 2025
- PDF Framework - RM1016 Holyport interchange · £11,909 · 28 Nov 2025
- PDF Framework - A5 EB WB M42 J10 - A5148 Wall SCRIM · £302,105 · 28 Nov 2025
- PDF Framework - A23 S Downs Way, Hickstead, Pyecombe Bundle - SDF Part 2 & 3 · £3,921,468 · 28 Nov 2025
- PDF Framework - A63 Brighton Street to Daltry Street Resurfacing · £555,028 · 28 Nov 2025
- PDF Framework - M6 J9 SB & NB Bescot Viaduct Pavement Hybrid Group 43 · £40,084 · 28 Nov 2025
- GI - BAM A38 signing · £43,972 · 28 Nov 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- JTP Improvement Programme · Suffolk Constabulary · £13,500
- S30119 Safety risk management continuous improvement · National Highways Limited · £72,976
- Strategic Advice for the Real Estate Vision Plan · Guy's and St Thomas' NHS Foundation Trust · £40,000
- Liverpool City Region Transport Model Update · Liverpool City Region Combined Authority · £1,200,000
- S30084 M60 Barton High Level Bridge - Bearing Adjustment - Cat 3 checks for the substructure AIP and GI survey reviews · National Highways Limited · £330,000
- S30128 Asset delivery asset maintenance (GM701) & inspection (GS801) update · National Highways Limited · £184,967
- S30113 IS055001 Auditing Services · National Highways Limited · £178,546
- S30102 Third Party NSIPs Technical Partner · National Highways Limited · £2,500,000
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.