Provision of services pertinent to the replacement of t-bar sections at the TTH
key details
| Value | £100,000 |
|---|---|
| Status | active |
| Category (CPV) | 51000000 |
| Region | Scotland |
| Deadline | 10 Jul 2026 |
| Procedure | open |
| OCID | ocds-r6ebe6-0000835790 |
description
Replacement of existing T‑bar steel sections forming part of the onshore test hub structural/support assemblies. The scope includes site survey and verification of existing T‑bar geometry and condition, design confirmation against current load cases and standards, offsite fabrication of new steel T‑sections (including cutting, drilling and preparation to match existing interfaces), installation of the new sections on site, and reinstatement of any connected components or services. The contractor shall provide all necessary temporary works, lifting and access arrangements, carry out welding and bolting to recognised structural steel standards, apply the specified protective coating system where required, and complete inspection, testing and certification (e.g. visual inspection, dimensional checks, and non‑destructive testing where indicated). As‑built drawings, material certificates and installation records for all replaced T‑bar sections are to be supplied on completion.
documents
- T-Bar Section
- T-Bar Plan View
- 60m Long Skid-Beam Plan View
- 60m Long Skid-Beam Plan View
- Provision of services pertinent to the replacement of t-bar sections at the TTH , contractNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
more from Net Zero Technology Centre Limited
- Replacement T-Bar Sections · £100,000 · 26 Jun 2026
- Provision of a 3.5t Flatbed Truck · £30,000 · 26 Jun 2026
- Provision of the construction of reinforced concrete bases for a pre-fabricated steel building. · 8 Apr 2026
- Provision of the Supply services to complete a new build office fit out · 23 Jan 2026
- Provision of the Supply and Installation of two Pre-Fabricated Steel Buildings · 23 Jan 2026
- Provision of the Supply and Installation Windows and doors for a pre-fabricated steel building. · 23 Jan 2026
- HOP2 Phase 3 Scope 3 - Assessment of Environmental Implications of Unplanned Hydrogen Releases for Offshore · £69,449 · 31 Jul 2025
- HOP2 Phase 3 Scope 5 - Economic Studies · 31 Jul 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Warden Call Upgrades · Gosport Borough Council
- T2720 Hire of Marquees and associated equipment · Belfast City Council · £380,000
- ELECTRICAL INSTALLATION AND CONTROL WIRING WORKS TO FOUR NEW STANDBY GENERATORS ADJACENT SUB-STATIONS AT CASTLE HILL HOSPITAL · HULL UNIVERSITY TEACHING HOSPITALS NHS TRUST · £100,352
- Installation of Fire Alarm Panels · Liverpool John Moores University
- Design and build Ilminster Skate park · Ilminster Town Council · £300,000
- OXLEVI – EV Charging Infrastructure · West Oxfordshire District Council
- Gloucestershire Sanctuary Scheme · Gloucester City Council
- TD2326 - Real-time information displays for bus stops 25/26 · DERBY CITY COUNCIL · £200,000
source
Published on Public Contracts Scotland. Contact details for named individuals are not reproduced on this site.