Sanday Linkspan Painting
key details
| Value | £140,000 |
|---|---|
| Status | complete |
| Category (CPV) | 45442120 |
| Region | Scotland |
| Deadline | 17 Jul 2020 |
| Procedure | open |
| OCID | ocds-r6ebe6-0000625233 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| Leask Marine Ltd | · | · | · |
description
Preparation, grit blasting and painting of Linkspan Bridge and supporting structures. Fitting new galvanised railings and Kee Klamp fittings and replacing bolts to linkspan structure
documents
- ESPD
- Appendix 1.2 - SI Drawings
- Appendix 1.2 - SI Drawings
- Appendix 1.2 - SI Drawings
- Appendix 1.2 - SI Drawings
- WI Appendix 2.1 - paint data sheets
- WI Appendix 2.1 - paint data sheets
- WI Appendix 2.1 - paint data sheets
- WI Appendix 2.1 - paint data sheets
- WI Appendix 2.1 - paint data sheets
- WI Appendix 2.2 - HSE guidance
- ESPD guidance
- WI Appendix 2.3 - kee klamp data
- SI Appendix 3.1 - Inspection Report
- SI Appendix 3.2 - testing for lead
- SI Appendix 3.3 - Site Photographs
- Ferry Timetable
- Tide data
- NEC Short Contract
- Appendix 1.1 - WI Drawings
- Appendix 1.1 - WI Drawings
- Appendix 1.1 - WI Drawings
- Appendix 1.1 - WI Drawings
- Appendix 1.1 - WI Drawings
- Appendix 1.2 - SI Drawings
- ESPD
- Appendix 1.2 - SI Drawings
- Appendix 1.2 - SI Drawings
- Appendix 1.2 - SI Drawings
- Appendix 1.2 - SI Drawings
- WI Appendix 2.1 - Paint Data Sheets
- WI Appendix 2.1 - Paint Data Sheets
- WI Appendix 2.1 - Paint Data Sheets
- WI Appendix 2.1 - Paint Data Sheets
- WI Appendix 2.1 - Paint Data Sheets
- WI Appendix 2.2 - HSE guidance
- ESPD guidance
- WI Appendix 2.3 - Kee klamp data
- SI Appendix 3.1 - Inspection Report
- SI Appendix 3.2 - Lead testing
- SI Appendix 3.3 - Site Photographs
- Orkney Tide Level Data
- Word .doc file
- Word .doc file
- Ferry Summer Timetable
- NEC Short Contract
- Appendix 1.1 - WI Drawings
- Appendix 1.1 - WI Drawings
- Appendix 1.1 - WI Drawings
- Appendix 1.1 - WI Drawings
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
more from Orkney Islands Council
- Provision of Stand Management · £340,000 · 10 Sept 2026
- Grounds Maintenance Services: 2027-2031 · £2,000,000 · 31 Aug 2026
- Invitation to Quote for the Supply of Services to Assist with the Isles Planned and Reactive Roads Maintenance Activities · £10,000 · 27 Aug 2026
- Provision of Planning Enforcement Direct Action Contractor · £750,000 · 17 Aug 2026
- GB-Kirkwall: TPPL Orkney Islands Council NEPO GM & P Lot 2 - 3 x 3.5t Diesel Forklift Trucks (New) (32385) · £143,364 · 14 Aug 2026
- Provision of 2026 Refit Services MV Thorsvoe · £170,000 · 4 Aug 2026
- ITT Provision of Security Services for Orkney Harbour Authority · £850,000 · 15 Jul 2026
- ITT for the Provision of Specialist Consultancy Services for Landscape and Visual Assessments · £150,000 · 10 Jul 2026
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Maintenance Works to Masts and Towers 2025 (defects identified in 2024) · Maritime and Coastguard Agency · £100,000
- Painterwork - Internal & External · Viewpoint Housing Association · £464,615
- Arts Bridge Remedial Repairs (non-trackside only) · University of Lincoln · £79,400
- Fit Out - WP12.7.1 - Painting and Sealants - Old Oak Common (S4) Station · Balfour Beatty VINCI Systra JV · £2,500,000
- Specialist Painting Services · NORTHERN GAS NETWORKS LIMITED
- Port of Sullom Voe Marine Infrastructure Maintenance Contract 2022 · Shetland Islands Council (Utilities) · £1,227,895
- INVITATION TO QUOTE FOR THE RECOATING OF EXTERNAL ELEMENTS AT FOUR LEISURE CENTRES WITHIN SOUTH RIBBLE · South Ribble Borough Council
- Greta Bridge Painting Maintenance · North Yorkshire County Council · £145,442
source
Published on Public Contracts Scotland. Contact details for named individuals are not reproduced on this site.