Diversion of cables - A30 Kennards House to Five Lanes Safety Improvement
key details
| Status | complete |
|---|---|
| Procedure | direct |
| OCID | ocds-h6vhtk-06a0c7 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| OCU Services Limited | · | · | active |
description
A30 Scheme (Kennards House to Five Lanes)-WO-211_61540Plusha - ( Sign P-TS43 ) - 3 days.
Cut & Cover - 5 days.
Two Bridges - P4 Terminal & VRS Installation - 3 days.
Polyphant - Grasscrete Instalaltion - 5 days. Demolish existing footway chamber and rebuild to carrigeway specification.
Post & Foundation Works ( NEW EB VAS Primary ) - 3 days . Relocation Of Existing Stone Monument - 5 Days
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 22 May 2026 | Contract details (UK7) | Procurement Act 2023 | 047721-2026 |
more from National Highways Limited
- Woodlands to Priory Court Transition · £31,899 · 30 Jul 2026
- Samaritans Communication Guidance 2026 · £15,000 · 30 Jul 2026
- Seamless Travel Across Networks (Manchester) · £0 · 29 Jul 2026
- M32 J2-J3 Eastville Traffic Counts · £208,950 · 28 Jul 2026
- M53 Raby Hall Deck Replacement – United Utilities C4 Diversion Works · £822,198 · 24 Jul 2026
- ITEP1234 - Street Manager payment · £13,500 · 24 Jul 2026
- Saturn Licence · £32,810 · 24 Jul 2026
- Maintenance and Response 2 Framework · £7,960,713,652 · 23 Jul 2026
all contracts from this buyer →
source
Published on Find a Tender. Contact details for named individuals are not reproduced on this site.