Transport Infrastructure Planned and Reactive Maintenance
key details
| Value | £4,255,802 (£5,106,962 inc. VAT) |
|---|---|
| Status | complete |
| Region | West Midlands |
| Procedure | open |
| OCID | ocds-h6vhtk-06747b |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| ASCOT SERVICES UK LIMITED | £4,255,802 | 26 Jul 2026 | pending |
description
This contract is for the provision of transport infrastructure planned and reactive maintenance across TFWM's asset portfolio (bus stations and park and ride sites), including proactive and reactive maintenance tasks, PAT testing and provision of a helpdesk service to manage tasks.
There are 5 key requirements set out in this specification, these are:
Planned Maintenance
Reactive Maintenance
Portable Appliance Testing
Helpdesk
Semi-Skilled Operative
These services will be delivered in line with the following objectives:
- The provision of Planned Preventative Maintenance (PPM) services to the Mechanical and Electrical (M&E) plant & equipment included within the contract
- The provision of reactive and emergency maintenance services to the Building Fabric and all M&E plant and equipment included within the contract
- The provision of "ad-hoc" escort / access assistance to all specialist Service Providers, engaged in the delivery of these services
- The carrying out of regular condition inspections across the facilities, at agreed intervals
- Ensuring that all Statutory and Legislative compliance maintenance works are carried out to all M&E plant & equipment covered in this specification
- The provision of specialist maintenance where required
- The provision of a comprehensive Planned and Reactive maintenance service across the facilities that complies with the standards and provisions as outlined within this specification
TfWM has made a commitment to and is working to develop good practice in infrastructure sustainability, including green and sustainable technologies in the design, refurbishment and maintenance of transport infrastructure facilities. The Service Provider will be required to demonstrate a commitment to sustainability by integrating sustainable development into their operating practices and culture throughout the Contract. This can be achieved by using low fuel consumption and emissions vehicles, optimising visits to each site, recycling of waste materials, disposing of any controlled waste in an approved manner, working with reusable components, using innovative designs and green technology or ethically sourced materials.
notice history
2 notices published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 26 Mar 2026 | Tender notice (UK4) | Procurement Act 2023 | 027641-2026 |
| 27 Jul 2026 | Contract award (UK6) | Procurement Act 2023 | 070962-2026 |
more from West Midlands Combined Authority
- Advisory Due Diligence Support · £1,600,000 · 23 Jul 2026
- Provision of Gauge Corner Restoration activities for Midland Metro Limited throughout the Birmingham City Centre. · 22 Jul 2026
- Provision of Verkada-based system for Midland Metro Limited · 22 Jul 2026
- CDM principal designer in relation to EV CATS · 21 Jul 2026
- Health Narrative procurement · 20 Jul 2026
- Highway Infrastructure Maintenance · £12,000,000 · 16 Jul 2026
- Transforming Real Time Passenger Information- Ref 05052-2023 · £8,840,666 · 15 Jul 2026
- Demolition Works - Longbridge Site · 7 Jul 2026
all contracts from this buyer →
source
Published on Find a Tender. Contact details for named individuals are not reproduced on this site.