Eagle Kitchen Block Refurbishment

Eagle & Swinethorpe Parish Council Published 6 Mar 2026 Find a Tender

key details

Statuscomplete
RegionNorth East, North West, Yorkshire and the Humber, East Midlands, West Midlands, East of England, London, South East, South West
OCIDocds-h6vhtk-0663ce

Award

SupplierValueDateStatus
Belton Construction · · active

description

Scope of works -

Demolition-

Strip out all windows and doors.
Remove existing fascia, guttering and downpipes
Remove existing roof covering
Fully strip out all internal fittings, ceilings and floor coverings
Strip out and isolate plumbing and electrical works.
Demolish internal wall
Form new door to Accessible WC

DPC-

  • Inject all existing walls with new DPC injection

Steel work-

  • Install new veranda steel framework.

Foundations-

Excavate & concrete 4 x pad foundations as engineers' details
Excavate & concrete strip foundation for dwarf wall

Brickwork-

Build new dwarf wall in engineering red bricks with brick on edge detail to the top of the wall.
We have allowed for 1 bricklayer plus materials for general brick work repairs to the existing building.

Foul and rainwater underground drainage-

  • We have allowed to install new under ground drains and manholes as shown on the architect's drawings with a connection on to the existing run. Back fill and make good.

Roof timbers-

We have allowed for all new roof timbers to the veranda only with Stirling board over the top and 9mmm ply to the underside as the engineer's detail.
We have allowed for new white UPVC fascia and guttering to the veranda and existing building.

Insulation-

All roof; walls and acoustic insulation is included as per the architects' drawings.
With the associated vapour barriers as specified

Internal walling-

All perimeter treated timber studwork as shown
All internal standard studs as shown
All metal stud walls with 18mm sheathing ply to both sides as shown.

Joinery-

MDF window boards to all windows
3 x vertical pipe boxings
1 new internal door set
Architraves to 1 internal door
Supply and fit new kitchen from Howdens
Supply and fit internal dividing panels to the women's and man's WC
Supply and fit fire blanket, extinguisher and signage

Plastering-

Plasterboard and skim ceilings
Plasterboard only the walls

Electrical works-

All electrical items as specified
Supply and fit Solar panels (PV)
All extractor fans x4
Panel heaters x4
Smoke alarms

Plumbing-

Remove and dispose of redundant services
Supply and fit 3no close coupled WC pans, cisterns and seats
Supply and fit 3no wall hung WHB's complete with TMV's and mixer taps
Supply and fit 1no urinal with exposed cistern and flush pipe
Supply and fit 1no Doc M pack with contrasting grab rails
Supply and fit 2no water heaters
Fit kitchen sink with allowance for 1no appliance

Wall finishes-

  • Supply and fit white rock to all walls.

Decorations-

Paint ceilings white
Paint internal exposed woodwork

Floor coverings-

  • Supply and fit floor coverings as specified with coved upstand External paving-
Begin to excavate the existing concrete slab and dispose of from site.
Supply and install 150mm of type 1 sub-base material to the entire area and compact in layers using heavy plant.
Supply and install necessary formwork.
Break points and levels to be agreed on site.
Supply and install corduroy hazard warning tactiles
Supply and install C30/35 ready-mix concrete to achieve approx. 100mm thickness.
Level, tamp and apply brushed finish
Spread topsoil and seed to make good, disturbed areas
Install 4 x kee klamp barriers near doors/windows

Quotation.

Cost of works £117'181.54+VAT

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
6 Mar 2026 Contract details (UK7) Procurement Act 2023 020244-2026

source

Published on Find a Tender. Contact details for named individuals are not reproduced on this site.