Barbican Renewal Construction Management
key details
| Value | £4,000,000 (£4,800,000 inc. VAT) |
|---|---|
| Status | complete |
| Category (CPV) | 71540000 |
| Region | London |
| Procedure | selective |
| SME suitable | Yes |
| OCID | ocds-h6vhtk-05f6c9 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| BSB Construction ltd | £5,123,447 | 5 Jul 2026 | pending |
description
The City of London Corporation (the City) has invited Tenders for the provision of Barbican renewal programme, Construction Management Services.
The Barbican Centre, which is a department of the City of London (CoL) Corporation, is seeking to appoint a Construction Manager (CM) to deliver Construction Management services for the Barbican Renewal Programme (BRP).
The appointment will commence in June 2026 and extend through to March 2030, with an estimated fee value of c. £4m against a total construction cost of approximately £176m. The CM will be appointed directly by the CoL and will act as the client's principal delivery partner, responsible for managing and coordinating a series of trade contractors engaged under separate contract with the CoL.
The Barbican Centre is a Grade II listed arts centre of international significance, situated within the wider Barbican Estate in the City of London. The Renewal Programme encompasses a broad and concurrent series of improvement, repair, and upgrade works across the Barbican Arts Centre (BAC), requiring careful sequencing and coordination to minimise disruption to visitors, building users, venue operations and nearby residents .
The CM will be required to operate within a live, occupied environment subject to significant heritage and conservation constraints, and to manage multiple workstreams progressing simultaneously across different areas. The Programme demands a high degree of logistical rigour, stakeholder sensitivity, and programme control; and the appointed CM will be expected to demonstrate commensurate experience in the delivery of complex, phased works within similarly constrained settings.
The scope of the CM appointment spans both pre-construction and construction phases. During the pre-construction phase, the CM will be responsible for developing and maintaining the master construction programme, advising on procurement strategy, and leading the procurement of trade contractor packages in conjunction with the existing Project Team of G&T, Greenway Associates, Allies & Morrison, Asif Khan Studio, Buro Happold and others.
The CM will also be required to assist in the submission and determination of a BSA Gateway 2 application, due to BAC recently being classified as a Higher-Risk Building (HRB).
During the construction phase, the CM will assume responsibility for the coordination and management of all trade contractors on site, overall site logistics, and the integration of individual package programmes into a coherent and deliverable whole.
The CM will maintain a proactive interface with the Project Team on all matters relating to cost reporting and change management and will hold principal responsibility for health and safety management across the site. Throughout the appointment, the CM will be required to lead and coordinate stakeholder and resident engagement activity as it relates to construction operations, working closely with Barbican Renewal, BAC, CoL and other key stakeholders to ensure that communication is managed effectively.
The duration of the contract is 44 months, subject to the right of the City (at its sole discretion) to exercise its right to extend the Contract by up to 12 months. The maximum length of the contract is therefore 56 months.
documents
- https://www.find-tender.service.gov.uk/Notice/017226-2026 , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
3 notices published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 16 Dec 2025 | Preliminary market engagement (UK2) | Procurement Act 2023 | 083394-2025 |
| 26 Feb 2026 | Tender notice (UK4) | Procurement Act 2023 | 017226-2026 |
| 6 Jul 2026 | Contract award (UK6) | Procurement Act 2023 | 063262-2026 |
more from The Mayor and Commonalty and Citizens of the City of London
- Salisbury Square Development - Landlord Network · £619,275 · 29 Jul 2026
- Safe Access Provision Over Bascule Chambers from Resting Blocks · £0 · 24 Jul 2026
- Barbican Centre Renewal – Furniture Designer · £200,000 · 24 Jul 2026
- City AM and City of London Corporation Partnership Agreement · £0 · 23 Jul 2026
- Building Advisor is a cloud-based building analytics platform · £0 · 23 Jul 2026
- Youth Services · £800,000 · 22 Jul 2026
- FPEP Moves Partner · £0 · 22 Jul 2026
- PTSI Survey and Investigation Works · 22 Jul 2026
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- CITY OF ARMAGH RFC EXTENSION AND CLUBROOM ENHANCEMENT SCHEME · Armagh, Banbridge & Craigavon Borough Council
- Project Lead for ADMC - Ashfield District Council · Nottinghamshire County Council · £297,928
- Regeneration Programme Management for Ashfield District Council · Nottinghamshire County Council · £238,342
- Courtauld Strand Campus - Construction Management · COURTAULD INSTITUTE OF ART · £4,905,000
- Kingston Small Sites Programme 2: Project Management and Cost Consultancy Services · The Royal Borough of Kingston upon Thames · £254,000
- CWC26007 City Development Programme Support · Wolverhampton City Council · £614,771
- LTC Investible Business & Transition Management Office future Phases · National Highways Limited · £8,582,440
- Construction Manager - Thicket Crescent and Thicket Road Energy Efficient Retrofit Works · London Borough of Sutton · £335,000
source
Published on Find a Tender. Contact details for named individuals are not reproduced on this site.