Shore Power Unit Groundworks (DA)
key details
| Status | complete |
|---|---|
| Procedure | direct |
| OCID | ocds-h6vhtk-05e9b7 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| Northern Powergrid (Yorkshire) plc shared | £90,354 | 13 May 2026 | active |
description
ORE Catapult has identified an opportunity to introduce shore power provision in the Port of Grimsby to support clean maritime demonstrations, building on existing Catapult facilities at the Operations and Maintenance Centre of Excellence (OMCE). The purpose of this direct award is to appoint Northern Powergrid to provide an electrical supply to this new electrical shore power unit in Grimsby.
notice history
4 notices published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 26 Nov 2025 | Transparency notice (UK5) | Procurement Act 2023 | 077461-2025 |
| 14 May 2026 | Transparency notice (UK5) | Procurement Act 2023 | 044222-2026 |
| 14 May 2026 | Contract award (UK6) | Procurement Act 2023 | 044253-2026 |
| 20 May 2026 | Contract details (UK7) | Procurement Act 2023 | 046292-2026 |
more from ORE Catapult
- Technical & Commercial Consultancy Services · 22 Jul 2026
- Decommissioning 15Mw Drive Train - Electrical · 15 Jul 2026
- Decommissioning 15Mw Drive Train - Mechanical · 15 Jul 2026
- Blyth Remedial Works · £400,000 · 10 Jul 2026
- Polygonal Roof Temp Building · 9 Jul 2026
- Handheld 3D Scanner · 8 Jul 2026
- Telecoms Installation · 26 Jun 2026
- Finance System Upgrade 2026 · 23 Jun 2026