Low Level Waste Repository (LLWR) Vault Optimisation and Capping Delivery

Nuclear Waste Services Limited Published 17 Jun 2026 Find a Tender
The value below is a framework or dynamic market ceiling: the maximum that could be spent across all call-offs, not the value of a single contract. Aggregate figures on this site exclude these to avoid double counting.

key details

Value£318,000,000 (£382,000,000 inc. VAT)
Statusplanned
Category (CPV) 45000000 +11 more
RegionNorth West
OCIDocds-h6vhtk-055c45

description

Nuclear Waste Services (NWS) is seeking a Contractor to provide all necessary Design & Engineering, Labour, Equipment, Plant & Materials to undertake all works associated with the delivery of Vault Optimisation and Capping Delivery. The contractor should have a proven track record in handling large scale Earthworks projects, equipped with necessary machinery and expertise to ensure the project is completed efficiently and on schedule.

Nuclear Waste Services operates the Low-Level Waste Repository (LLWR) Site in West Cumbria on behalf of the Nuclear Decommissioning Authority. The LLWR Site is the national disposal facility for Low Level Waste (LLW) arising from the nuclear industry and wider industries, such as medical and defence.

Protecting and developing the Repository’s radioactive waste disposal capability is a long-term programme of works, over the next 100+ years, that will provide future disposal facilities and protection of people and the environment from the disposed waste through to closure of the Repository Site. In the shorter term, over the next 15 years, the focus is on installing closure engineering works for long-term environmental protection from the wastes currently disposed of in Vault 8 and the adjacent legacy disposal trenches as well as constructing additional disposal capacity in the form of new LLW vaults.

The project under NWS covers the following packages of works:

  • Final Capping (provide an engineered protective cover) over all the Low Level Waste that has been disposed of in the trenches and vaults.
  • Design of an extension to the existing disposal Vault (V9), retaining wall to allow partial closure seal of V9, new Leachate Management System and weather protection warehousing for HHISO containers awaiting disposal.
  • Construction of an extension to the existing LLW disposal Vault (V9), retaining wall, partial closure seal of V9, new Leachate Management System and weather protection warehousing for HHISO containers awaiting disposal.
  • Design of an Interim Cap over the closed section of Vault 9.
  • Construction of an Interim Cap over the Low Level Waste that has been disposed in Vault 9.

Works include but is not limited to;

  • Earthworks, including excavation and Backfill work
  • Provision of associated plant
  • Site Clearance
  • Groundworks
  • Piling
  • Aggregates
  • Demolition
  • Drainage
  • Engineering & Construction Works
  • Design
  • Land remediation

notice history

5 notices published against this procurement.

PublishedTypeRegimeNotice
9 Jul 2025 Pipeline notice (UK1) Procurement Act 2023 038699-2025
21 Jul 2025 Preliminary market engagement (UK2) Procurement Act 2023 041533-2025
16 Sept 2025 Preliminary market engagement (UK2) Procurement Act 2023 057045-2025
24 Oct 2025 Preliminary market engagement (UK2) Procurement Act 2023 068240-2025
17 Jun 2026 Preliminary market engagement (UK2) Procurement Act 2023 057001-2026

more from Nuclear Waste Services Limited

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Find a Tender. Contact details for named individuals are not reproduced on this site.