Automated People Mover (APM) Infrastructure
key details
| Value | £154,000,000 (£184,800,000 inc. VAT) |
|---|---|
| Status | planned |
| Category (CPV) | 45234000 +1 more |
| SME suitable | Yes |
| OCID | ocds-h6vhtk-0519dd |
description
The HS2 Phase One route is from London Euston to the West Midlands and includes the development of high-speed rail stations at London Euston, London Old Oak Common, Birmingham Interchange and Birmingham Curzon Street.The proposed HS2 Birmingham Interchange Station will be situated approximately 20 km to the southeast of Birmingham city centre, close to Birmingham Airport. An Automated People Mover (APM) is required to transport passengers from adjacent areas to the Interchange Station and the wider HS2 network. The APM network will consist of a maintenance facility and four stops detailed herein:
| I. | Interchange Station stop; |
| II. | National Exhibition Centre stop; |
| III. | Birmingham International Railway Station stop; and |
| IV. | Birmingham Airport stop. |
The APM has been designed as an elevated mass transit system, which will transport passengers between those stops detailed above. The APM route will consist of a 2.3km long viaduct, four stops and a maintenance facility. The Interchange Station Stop is at ground level and the three other stops and maintenance facility are on the viaduct (above ground level). The route has several major crossings to navigate, such as the M42 motorway, the West Coast Main Line (WCML) and Pendigo Lake at the National Exhibition Centre (NEC) site.
The key design features of the APM Infrastructure include reinforced central concrete piers, weathered steel deck and escape walkway gratings throughout the entirety of the track. To minimise impact to the existing developed site and public roads, the entire 2.3km route is on an elevated viaduct. This is made up of a range of single and twin track at various points along the route to allow trains to pass each other.The piers range from 6 metres high to 14 metres, depending on the topography along the route. In order to maintain a consistent level for the viaduct, the columns will need to vary in height.
The stops at Birmingham Airport and at Interchange Station will have a single platform face and the intermediate stops at the NEC and Birmingham International Railway Station have two platform faces. The platforms vary from 36m to 40m long and all platforms are fully covered with canopies and have step free access.
The APM Infrastructure scope includes the detailed design and delivery of all piers, viaducts, APM stops, the APM maintenance facility as well as temporary works. The APM Infrastructure Contractor will be the Principal Contractor for the works and will be responsible for managing the APM Systems Contractor as well as nominated HS2 Contractors during these works. The APM Infrastructure Contractor will be responsible for managing all the interfaces and access for the works. Further details on interfacing contractors will be provided in the Tender documentation for the APM Infrastructure procurement.
notice history
2 notices published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 21 May 2025 | Pipeline notice (UK1) | Procurement Act 2023 | 023602-2025 |
| 26 May 2026 | Pipeline notice (UK1) | Procurement Act 2023 | 048677-2026 |
more from High Speed Two (HS2) Limited
- Interim Maintenance Contracts (IMC) · £1,034,000,000 · 1 Jun 2026
- Plant Materials · £19,000,000 · 27 May 2026
- High Speed Two (HS2) Limited, Phase One Stations - Framework Agreement for Station Control Lines · £22,000,000 · 21 May 2025
- Contruent Enterprise (PRISM) system support (2025) · 15 May 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Mid Cornwall Metro Implementation Agreement · Cornwall Council · £29,178,009
- Mid-Cornwall Metro · Cornwall Council · £2,499,687
- Earthing and Bonding · Transport for Wales · £12,000,000
- High Voltage (HV) Power Framework · London Underground Limited (LUL)
- Feltham Phase 5 Civils Works · Network Rail Infrastructure Ltd · £6,473,365
- Tramway Maintenance Services · Blackpool Council · £500,000
- Northumberland Park Signalling Depot Advanced Works Track Circuit Conversion · Transport for London · £825,156
- Site Support Services Framework · Transport for London · £347,880
source
Published on Find a Tender. Contact details for named individuals are not reproduced on this site.