key details
| Value | £6,000,000 |
|---|---|
| Status | complete |
| Category (CPV) | 71530000 +1 more |
| Region | London |
| Deadline | 18 Sept 2024 |
| Procedure | selective |
| OCID | ocds-h6vhtk-047c17 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| Freehaus Design Limited | · | · | active |
description
The Ministry of Housing, Communities & Local Government (MHCLG) (the 'Authority'), actively supported by the Royal Institute of British Architects ('RIBA') has concluded a procurement on behalf of the Grenfell Tower Memorial Commission ('GTMC') to secure multi-disciplinary design services from a multi-disciplinary design team (MDDT) to develop the design for the Grenfell Memorial. The lead designer awarded the contract is required to commence design activity at RIBA Stage 0 (Strategic Definition) to enable bereaved, survivors and immediate community to influence the development of design. The design will be iteratively developed under a community-led design process and the RIBA Plan of Work.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 9 Jul 2024 | Contract notice (F02) | Earlier regulations | 020982-2024 |
more from Ministry of Housing, Communities & Local Government
- Independent Evaluation of City Deal, Growth Deal and Devolution Deals · £1,950,000 · 15 Jul 2026
- Market Warming Event for Research and Evaluation Contracts for MHCLG · £19,000,000 · 27 May 2026
- Grenfell Tower Principal Contractor · 25 Apr 2025
- Standby Management Consultancy and Professional Services (Operational) · £18,225,000 · 13 Jan 2025
- Grenfell Tower Scaffolding Hire · 21 Nov 2024
- Grenfell - Community Engagement · £150,000 · 19 Nov 2024
- Fire Safety - Trigger Thresholds · £185,933 · 21 Oct 2021
- BSP Legal Services Contract Extension up to April 2024 (from April 2022) · £475,000 · 20 Oct 2021
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Melksham Hospital Boiler Replacement and Window Replacement Scheme · NHS PROPERTY SERVICES LIMITED · £75,290
- Main Works EIA Scoping Report · North Wes Anglia NHS Foundation Trust · £34,228
- Cost Consultant Appointment for the Maternity Assessment Unit Capital Scheme · Guy's and St Thomas' NHS Foundation Trust · £177,470
- Gassiott House Student Hub - Project Manager · Guy's and St Thomas' NHS Foundation Trust · £136,553
- Ward Refurbishment Programme - QS · Guy's and St Thomas' NHS Foundation Trust · £76,763
- Ward Refurbishment Programme Procurement Support · Guy's and St Thomas' NHS Foundation Trust · £27,000
- Electrical Consultant for Substations 7 and 8 · Guy's and St Thomas' NHS Foundation Trust · £40,000
- Architect, Albert, Hillyers, Mitchener, Somerset Wards · Guy's and St Thomas' NHS Foundation Trust · £399,453
source
Published on Find a Tender. Contact details for named individuals are not reproduced on this site.