Pre-Commercial Procurement: Design, develop, and demonstrate wave energy converter systems (EuropeWave PCP).
key details
| Value | €16,333,333 |
|---|---|
| Status | complete |
| Category (CPV) | 73100000 +3 more |
| Deadline | 1 Oct 2021 |
| Procedure | open |
| OCID | ocds-r6ebe6-0000650423 |
Awards (7)
This procurement was awarded to 7 suppliers. Values shown are per-award; the notice total is €16,333,333.
| Supplier | Value | Date | Status |
|---|---|---|---|
| AMOG Consulting Ltd shared | · | · | · |
| Arrecife Energy Systems shared | · | · | · |
| Bombora Wave Power Europe Ltd shared | · | · | · |
| CETO Wave Energy Ireland Limited shared | · | · | · |
| IDOM Consulting, Engineering, Architecture S.A.U. shared | · | · | · |
| Mocean Energy Ltd shared | · | · | · |
| Waveram Limited shared | · | · | · |
description
This contract award notice informs interested operators about the outcome of a tender.
On 7 July 2021, a contract notice was published in TED as part of the EU project EuropeWave to purchase R&D services from a number of R&D providers in parallel (PCP procurement).
The PCP procurement compared competing alternative solution approaches to address the following challenge:
The EuropeWave PCP aims to accelerate the design, development, and demonstration of cost-effective wave energy converter (WEC) systems to produce clean electricity, advance promising designs for wave energy converter systems to a point from which they are ready to proceed to a first of a kind commercial-scale design and testing programme and commercial exploitation through other national/regional programmes and/or private sector investment.
The main technical challenges to be addressed are:
-Performance – obtain quantitative evidence of power capture and conversion capability and increase confidence in yield predictions from simulations.
-Survivability – demonstrate effective survival strategies.
-Availability – demonstrate levels of availability through reliable prototype operation.
-Affordability – increase confidence in estimations of the technology costs (capital and operational) and the requirements to achieve a LCOE which is competitive in the target market.
The culmination of the EuropeWave PCP programme (Phase 3) will see prototypes, at substantial scale and with fully representative subsystems, deployed at the open-water facilities of the European Marine Energy Centre (EMEC) in Scotland and the Biscay Marine Energy Platform (BiMEP) in the Basque Country and operated for a minimum period to demonstrate device performance, reliability and cost. Physical model testing in earlier phases is expected to take place in Instituto de Hidráulica Ambiental de Cantabria (IHC) and FloWave Ocean Energy Research Facility (FloWave).
This joint procurement exercise is being undertaken by Wave Energy Scotland in its role of lead procurer acting in the name and on behalf of the procurers of the EuropeWave buyers group:
-Wave Energy Scotland
-Ente Vasco de la Energía
documents
- TD01 Request for Tenders
- TD05 Technical Offer - Annex A - Abstract
- TD05 Technical Offer - Annex B - Technology Risk Register
- TD05 Technical Offer - Annex C - Project Risk Register
- TD06 Financial Offer and Cost Breakdown
- TD07 Form 1 -General Declaration
- TD07 Form 1 Annex A - Consortium Power of Attorney
- TD07 Form 1 Annex B - Subcontractor Declaration
- TD07 Form 1 Annex C - Project Team Details
- TD07 Form 2- Exclusion Criteria Declaration
- TD07 Form 3 - Selection Criteria Declaration
- TD02 PCP Challenge
- TD07 Form 4 - Compliance Criteria Declaration
- TD07 Form 4 Annex A - Background
- TD07 Form 5 - Financial Offer - Phase 1 Declaration (Form of Tender)
- TD08 Market Consultation - Questions and Answers
- TD09 Documentation Checklist
- HIE Conflicts of Interest Policy
- WES Conflicts of Interest Guidance
- EuropeWave - information webinar Q&A
- TD06 Financial Offer and Cost Breakdown v2
- TD02 Annex A Phase 1 Testing
- TD02 Annex B Phase 1 Test Site Fact Sheet
- TD03 Framework Agreement
- TD04 Terms and Conditions - Phase call-off contract (Phase 1)
- TD04 On demand Advance Payment Guarantee
- Useful links - extracts from RfT
- TD05 Technical Offer
- Pre-Commercial Procurement: Design, develop, and demonstrate wave energy converter systems (EuropeWave PCP). , contractNotice
- Pre-Commercial Procurement: Design, develop, and demonstrate wave energy converter systems (EuropeWave PCP). , awardNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 2 Jul 2021 | Contract notice (F02) | Earlier regulations | 015241-2021 |
more from Lead Procurer: Wave Energy Scotland Limited
- Prior information notice: Design, develop, and demonstrate wave energy converter systems (EuropeWave PCP) · €16,333,333 · 26 Feb 2021
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- TCAT - Liver Ductal Project · The Common Services Agency (more commonly known as Public Services Delivery Scotland) (PSD Scotland) · £117,846
- Framework for Applied Science Technology Engineering Requirements (FASTER) · Met Office · £45,600,000
- Hot Isostatic Pressing (HIP) of Plutonium Powders – Installation and commissioning of equipment in Central Laboratory · Nuclear Decommissioning Authority
- DSIT NI Project BARBARA EOI · DSIT · £106,796
- OPM-MEG (UoB) · MINISTRY OF DEFENCE · £549,831
- Award of DECC Independent Evaluation of Sustainable Scotland Network · Scottish Government · £45,406
- Food Data Infrastructure and Governance · DEPARTMENT OF ENVIRONMENT, FOOD AND RURAL AFFAIRS · £0
- Harwell - Strategic Enablers GameChanger BEPO · Nuclear Restoration Services · £140,000
source
Published on Find a Tender. Contact details for named individuals are not reproduced on this site.