ABLE MARINE ENERGY PARK - MAIN QUAY WORKS
key details
| Value | £285,000,000 |
|---|---|
| Status | complete |
| Category (CPV) | 45241100 +3 more |
| Region | Yorkshire and the Humber |
| Deadline | 10 Mar 2021 |
| Procedure | selective |
| OCID | ocds-h6vhtk-02913a |
Awards (2)
This procurement was awarded to 2 suppliers. Values shown are per-award; the notice total is £285,000,000.
| Supplier | Value | Date | Status |
|---|---|---|---|
| Eiffage Genie Civil Marine (consortium lead) shared | · | · | active |
| Jan De Nul n.v. shared | · | · | active |
description
In summary, the Works comprises a Design and Construct contract for a new quay at Able Humber Port, Rosper Road, North Killingholme, DN40 3DZ, as part of the wider Able Marine Energy Park (AMEP) development.
The Works are to be completed and handed over in stages, each stage to be taken into operational use by the Contracting Entity while the remaining stages are completed by the Principal Contractor.
The Scope of Works as described in the Employer's Requirements includes but is not limited to the following:
- marine & landform engineering design;
- marine & landform engineering detailing;
- marine & landform engineering specification;
- risk assessments & methods statements (RAMS);
- specialist subcontractor & supplier procurement;
- materials, plant & equipment delivery;
- marine & landform construction;
- testing, commission & training;
- securing all consents, discharge of existing, new, or additional conditions; and
- compliance with all applicable legislative & regulatory requirements.
notice history
2 notices published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 8 Feb 2021 | Utilities contract notice (F05) | Earlier regulations | 002515-2021 |
| 22 Dec 2021 | Utilities contract award (F06) | Earlier regulations | 032100-2021 |
more from Able Humber Ports Limited
- AMEP AREA K MONOPILE FACILITY WORKS · £125,000,000 · 13 Aug 2021
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Orkney Harbours Masterplan Phase 1 - Scapa Deep Water Quay (SDWQ) · Orkney Islands Council (Harbour Authority) · £200,000,000
- Weymouth Harbour Quay Wall D - Strengthening Works · Weymouth & Portland Borough Council · £1,200,000
source
Published on Find a Tender. Contact details for named individuals are not reproduced on this site.