Dover White Cliffs Feasibility Study Design
The value below is a framework or dynamic market ceiling: the maximum
that could be spent across all call-offs, not the value of a single contract.
Aggregate figures on this site exclude these to avoid double counting.
key details
| Value | £49,500 |
|---|---|
| Status | complete |
| Category (CPV) | 71530000 |
| Region | South East |
| Deadline | 22 Jul 2022 |
| Contract start | 27 Jul 2022 |
| Contract end | 26 Oct 2022 |
| SME suitable | No |
| OCID | ocds-b5fd17-f45f767e-1d21-48f4-b574-ab44ee516644 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| WSP UK Limited | £49,500 | 25 Jul 2022 | active |
description
Undertake a feasibility study for the development of the Dover White Cliffs site.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 22 Aug 2022 | Award (award) | · | b179e7b5-e90d-4494-822d-68a8e53b9e5a-565482 |
more from DfTc - Department for Transport
- RSGR0002 Rail Evaluation Call-Off Contract · £3,000,000 · 27 Jul 2026
- Supply of ServiceNow Licences · £3,000,000 · 26 Jul 2026
- Provision of Value of a Life Year Research (VOLY): Lot 4 Peer Review · £74,008 · 24 Jul 2026
- Provision of Value of a Life Year Research (VOLY): Lot 3 Supplementary Empirical Research · £182,737 · 24 Jul 2026
- Provision of Value of a Life Year Research (VOLY): Lot 2 Advice on the maintenance and application of the values · £90,190 · 24 Jul 2026
- TANL3071 - Provision of Value of a Life Year Research (VOLY): Lot 1 Primary Research · £1,298,901 · 24 Jul 2026
- Provision of Evaluation Research Support - Lot 2 · £1,250,000 · 23 Jul 2026
- Provision of Evaluation Research Support - Lot 1 · £1,250,000 · 23 Jul 2026
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Melksham Hospital Boiler Replacement and Window Replacement Scheme · NHS PROPERTY SERVICES LIMITED · £75,290
- Main Works EIA Scoping Report · North Wes Anglia NHS Foundation Trust · £34,228
- Cost Consultant Appointment for the Maternity Assessment Unit Capital Scheme · Guy's and St Thomas' NHS Foundation Trust · £177,470
- Gassiott House Student Hub - Project Manager · Guy's and St Thomas' NHS Foundation Trust · £136,553
- Ward Refurbishment Programme - QS · Guy's and St Thomas' NHS Foundation Trust · £76,763
- Ward Refurbishment Programme Procurement Support · Guy's and St Thomas' NHS Foundation Trust · £27,000
- Electrical Consultant for Substations 7 and 8 · Guy's and St Thomas' NHS Foundation Trust · £40,000
- Architect, Albert, Hillyers, Mitchener, Somerset Wards · Guy's and St Thomas' NHS Foundation Trust · £399,453
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.