Skills and Flexible Resource Innovation Project - Phase 2
key details
| Value | £75,000 |
|---|---|
| Status | complete |
| Category (CPV) | 73000000 |
| Deadline | 26 Sept 2022 |
| Contract start | 30 Jan 2023 |
| Contract end | 30 Mar 2023 |
| Procedure | selective |
| SME suitable | Yes |
| OCID | ocds-b5fd17-bffd4e0c-e613-4f4e-bb60-344040f4057e |
Awards (2)
This procurement was awarded to 1 suppliers. Values shown are per-award; the notice total is £75,000.
| Supplier | Value | Date | Status |
|---|---|---|---|
| Nous Group | £75,000 | 27 Jan 2023 | active |
| Nous Group | £50,000 | 11 Oct 2022 | active |
description
Phase 2 was included an an option in the Phase 1 Tender.
Requirement
We require a partner to work with us to explore the art of the possible to meet current and changing demand for our services.
For this second piece of work (phase 2) we want to explore the priority areas identified in phase 1.
- E.Access to skills and capability
- F.Optimise resource and capacity
- G.Drive customer focussed culture
A delivery partner will need to work with key stakeholders to answer the following questions
- What capabilities and skills do we need to meet future demand for our services, what are the options for accessing these and what are the wider organisational implications?
- How can we optimise our resource and capacity, and what are the wider organisational implications?
- What does a successful culture for hybrid working look like, and how can we foster this over time?
- What are the timelines and level of investment for each of the above?
Contract deliverables
- A.We understand
the options and
approaches to
develop and/or
access future
skills and
capability
- Produce a report setting out the options and approaches
we could consider, to develop and/or access future skills
and capability.
- a)Research should consider how other organisations use different methods to develop and/or access skills and capability.
2
- b)Options analysis should include assessment against agreed success criteria, indicative timeline, activity, benefits, risks, dependencies, wider implications, and high-level costing.
- B.We understand
the options and
approaches to
optimise
resource and
capacity
- Produce a report setting out the options and approaches we could consider, to optimise resource and capacity.
- a)Research should consider how other organisations use different methods to optimise resource and capacity
- b)Options analysis should include assessment against agreed success criteria, indicative timeline, activity, benefits, risks, dependencies, wider implications, and high-level costing.
- C.We understand
the options and
approaches to
drive a
customer
- Produce a report setting out the options and approaches we could consider, to drive a customer focussed culture.
- a)Research should consider how other organisations use different methods and approaches to optimise workplace culture.
- b)Analysis should assess current state of culture, areas of strength and gaps (and how this is impacted within a hybrid organisation).
- c)Options analysis should include assessment against agreed success criteria, indicative timeline, activity, benefits, risks, dependencies, wider implications, and high-level costing.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 30 Jan 2023 | Award (award) | · | 82fef8f0-005c-4331-b708-726800552cbd-609782 |
more from The Planning Inspectorate
- Technology and associated services · 27 May 2026
- Welsh Translation Services · £130,000 · 24 Mar 2026
- Horizon Scanning Tool · £31,500 · 9 Mar 2026
- Horizon SSL Certificates x 6 · £12,000 · 22 Oct 2025
- CRM Software Subscriptions, User Support and Technical Services · £200,241 · 14 Aug 2025
- Cyber Security as a Service · £1,500,000 · 23 Jun 2025
- Planning Resource, DCP Online & COMPASS Subscription · £79,995 · 17 Feb 2025
- Management Consultancy · £10,000,000 · 17 Feb 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- PS26172 - USB Technical Expert Support Service · DSIT · £1,500,000
- Best Start Family Hubs Evaluation · Department for Education · £4,762,158
- Provision of Specialist Local Government Reorganisation (LGR) Programme Support Services for Mid, North East and West Essex · Epping Forest District Council · £240,000
- Award of Invitation To Quote for Preparation of a Programme of Works for the Rosyth River Restora... · Fife Council · £75,000
- Award of DLGH - Compliance plan - 6 month Review of implementation of Compliance Plan Guidance · Scottish Government · £45,750
- Award of DLGH -Technical support during the stage 2 consultation for energy standards for new dom... · Scottish Government · £13,310
- PS26210 - RAF 011/2627 -Understanding compliance and supporting sustainable enforcement of PRS domestic and non-domestic MEES · DESNZ · £213,347
- Subject Classification Work for UK Legislation · The National Archives · £228,750