gvtcx

Thames Tideway Tunnel - C405 Main Works West - Rising Main Ducting Works

BIP SOLUTIONS LIMITED Published 8 Jun 2021 Contracts Finder

key details

Value£1
Statuscomplete
Category (CPV) 44114220 +1 more
RegionLondon
Deadline18 Jun 2021
Contract start25 Aug 2021
Contract end28 Aug 2022
Procedurelimited
SME suitableNo
OCIDocds-b5fd17-9adddb36-7ed9-41f9-a6ac-e97db10cfa1f

Award

SupplierValueDateStatus
not named £419,676 24 Aug 2021 active

description

The Thames Tideway Tunnel project (the Project) will control CSO discharges by intercepting and diverting combined sewage flows into a new storage and transfer tunnel. The main tunnel will run from Acton Storm Tanks in west London to Abbey Mills Pumping Station in the east, where it will connect to the Lee Tunnel, which will transfer the combined sewage to Beckton Sewage Treatment Works for treatment. The Project extends from Acton Storm Tanks in west London, to Abbey Mills Pumping Station in east London. The Project includes associated works at Beckton STW, Shad Thames Pumping Station and Bekesbourne Street.

The geographic layout of the Project and local authorities through which it passes is shown in Figure 1.

The Project comprises:

  • a.tunnels:
  • i.a main tunnel which will capture and store combined sewage from CSOs along its route and transfer it to Abbey Mills Pumping Station, from where the Lee Tunnel will transfer it for treatment at Beckton Sewage Treatment Works
  • ii.11 connection tunnels, which will link flows from CSOs to the main tunnel.
  • b.Worksites:
  • i.five main tunnel Worksites (drive and/or reception sites)
  • ii.16 CSO Worksites
  • iii.two System modification Worksites Thames Tideway Tunnel
  • iv.works at Beckton Sewage Treatment works.

Scope of Works

Temporary works design and provisions Trench excavations

Installation of free issue 900mm dia ducting Connection of ducting into third party assets Air testing of ducting

Backfilling

Returned quotations will be evaluated by BMB JV's (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty) Procurement team in conjunction with our design and engineering teams.

Quotations will be evaluated based on;

Cost

Timeliness of return

Adherence to and demonstration of understanding of the drawings and specifications provided at this point.

Provision of accurate product specifications to accompany the quotation.

Supplier experience of similar projects,evidence of this will be requested should the initial quotation be of interest.

Should the candidate supplier be shortlisted they will then be contacted directly by a member of the BMB Procurement Team within two weeks of shortlisting to discuss the requirement in detail.

BMB Joint Venture (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty)

Acton Storm Tanks Worksite

Additional information: Acton Storm Tanks Worksite

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
3 Mar 2022 Award (award) · 4ec75052-3072-42af-a506-d241d8d0b89a-513610

more from BIP SOLUTIONS LIMITED

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.