Sewer Flow Modelling Expertise and Technical Support
key details
| Value | £7,926 |
|---|---|
| Status | complete |
| Category (CPV) | 79411000 |
| Region | West Midlands, London |
| Deadline | 14 Aug 2019 |
| Contract start | 3 Sept 2019 |
| Contract end | 31 Dec 2019 |
| Procedure | open |
| SME suitable | Yes |
| OCID | ocds-b5fd17-71f2d620-c451-4957-9995-1c6ccce6f864 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| Richard Allitt Associates Ltd | £7,926 | 1 Sept 2019 | active |
description
The Supplier will review the sewer capacity modelling that was previously undertaken to determine whether the approach taken to modelling the available capacity in the sewer system was in-line with the wastewater company's own internal guidance and industry practices at the time that the work was carried out. This will include:
consideration of whether the modelling parameters used in the modelling work were reasonable;whether the scope of the modelling work undertaken was suitable to support decisions on the available capacity of the sewer system; modelling the available capacity of the sewer system to confirm the original sewer capacity modelling results; and review the wastewater company's approach to determining the expected peak flows from the new development.
If the Supplier concludes that there are concerns that the approach taken by the wastewater company to model the available capacity of the sewer was not reasonable, the Supplier will also be required to provide its view on what a reasonable approach would be and use the wastewater company's sewer model for the area to assess the available capacity in the sewer network in the area of the development site.In order to undertake this work, the Supplier will make arrangements with the wastewater company to be provided with: the initial assessment of the available capacity in the sewer network; the model verification report for the original model;information about the wastewater company's internal guidance; and the wastewater company's internal standards and practices that it uses when assessing the available capacity in its sewer network. This will contain commercially sensitive information. As a result, the Supplier will be required to enter into an agreement with the wastewater company to enable the Supplier to receive this information on a confidential basis.If the Supplier requires information about the standard industry practices for assessing sewer capacities from other wastewater companies it will be required to obtain this information from other wastewater companies itself.The successful Supplier's findings will help to inform Ofwat's determination on whether there was available capacity in the existing sewer network to accommodate the additional flows from the new development site without negatively impacting existing customers. The Supplier will be reviewing the modelling work undertaken to support both the planning and design stage of the capital scheme which was undertaken. The Supplier will be required to have access to the relevant software that is necessary for it to undertake any modelling work. This will not be provided by Ofwat. The modelling work that the Supplier will be reviewing was undertaken in 2014-2015. As a result, the Supplier will be required to have access to the appropriate version of the software, which may not be the most recent version. The relevant software is InfoWorks CS 11.5 and InfoWorks ICM.
Additional information: For Further Information, please contact: procurement@ofwat.gov.uk
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 24 Feb 2020 | Award update (awardUpdate) | · | fb0beec9-5276-4878-8ecb-2bc150a04648-345659 |
more from Water Services Regulation Authority (Ofwat)
- Interim Learning and Organisation Development Partner · £60,960 · 17 Dec 2021
- Interim Head of HR Transformation & Operations · £1,366,045 · 17 Dec 2021
- Interim Finance Business Analyst · £89,073 · 17 Dec 2021
- Impact Evaluation · £73,000 · 17 Dec 2021
- Interim Principal Economist · £83,168 · 22 Nov 2021
- 2 x Interim Principal Economists · £52,000 · 18 Nov 2021
- Delivery Partner Support for in-period Outcome Delivery Incentive Assessments (ODIs) · £1,560,000 · 18 Nov 2021
- Regional co-ordination · £53,410 · 18 Nov 2021
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- IMx - Phase 2 · Environment Agency · £592,730
- nterim Strategic Leadership Support for Housing Quality and Investment Services · London Borough of Lewisham · £100,000
- Security review and crisis response plan · DEFRA · £83,112
- Executive Leadership and Development Support · NHS E · £240,000
- Business Development Partner for Youth Justice Service · Liverpool City Council · £70,000
- BHNFT - Consultancy and Advisory Services for Health Framework · Barnsley Hospital NHS Foundation Trust · £126,960
- Negotiated Contract for the Support of South Lanarkshire Council’s Transformational Review of Customer Engagement · South Lanarkshire Council · £63,750
- Aggregate Working Parties Secretariat · Ministry of Housing, Communities and Local Government (MCHLG) · £606,664
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.