Thames Tideway Tunnel - C405 Main Works West - secondary lining of the King Georges Park Shaft
key details
| Value | £100,000 |
|---|---|
| Status | complete |
| Category (CPV) | 03419100 |
| Region | London |
| Deadline | 1 Feb 2019 |
| Contract start | 1 Apr 2019 |
| Contract end | 17 May 2019 |
| SME suitable | Yes |
| OCID | ocds-b5fd17-6ac9b660-2761-4717-82dd-b743a5095893 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| not named | £41,700 | 12 May 2019 | active |
description
The Thames Tideway Tunnel project (the Project) will control CSO discharges by intercepting and diverting combined sewage flows into a new storage and transfer tunnel. The main tunnel will run from Acton Storm Tanks in west London to Abbey Mills Pumping Station in the east, where it will connect to the Lee Tunnel, which will transfer the combined sewage to Beckton Sewage Treatment Works for treatment. The Project extends from Acton Storm Tanks in west London, to Abbey Mills Pumping Station in east London. The Project includes associated works at Beckton STW, Shad Thames Pumping Station and Bekesbourne Street.
The geographic layout of the Project and local authorities through which it passes is shown in Figure 1.
The Project comprises:
- a.tunnels:
- i.a main tunnel which will capture and store combined sewage from CSOs along its route and transfer it to Abbey Mills Pumping Station, from where the Lee Tunnel will transfer it for treatment at Beckton Sewage Treatment Works
- ii.11 connection tunnels, which will link flows from CSOs to the main tunnel.
- b.Worksites:
- i.five main tunnel Worksites (drive and/or reception sites)
- ii.16 CSO Worksites
- iii.two System modification Worksites Thames Tideway Tunnel
- iv.works at Beckton Sewage Treatment works.
The Main Works West - Contract 405: all works from and including the Acton Storm Tanks shaft to and including the Carnwath Road Riverside shaft, as well as the Frogmore connection tunnel from Carnwath Road Riverside shaft to King George's Park shaft.
This works package is for the provision of the design, supply and supervision of the slipform equipment for the secondary lining of the King Georges Park Shaft supply and delivery to site of Timber packers TTT West,
The Subcontractor will be required to provide the following deliverables to fulfil the requirements of this Subcontract:
| • | Provide the designs and calculations for the formwork (slipform) scheme for the King Georges Park shaft (to be checked by the Contractor) |
| • | RAMS documents |
| • | Supervisor for the duration of the work |
| • | Driver of the slipform equipment for the duration of the work |
| • | All equipment required |
| • | Product specification data sheet |
| • | Delivery of the above to site |
| • | Trial slide at the Contractor's yard at West Drayton |
The works are programmed for April 2019
Returned quotations will be evaluated by BMB JV's (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty) Procurement team in conjunction with our design and engineering teams.
Quotations will be evaluated based on;
Cost
Timeliness of return
Adherence to and demonstration of understanding of the drawings and specifications provided at this point.
Provision of accurate product specifications to accompany the quotation.
Supplier experience of similar projects,evidence of this will be requested should the initial quotation be of interest.
Should the candidate supplier be shortlisted they will then be contacted directly by a member of the BMB Procurement Team within two weeks of shortlisting to discuss the requirement in detail.
BMB Joint Venture (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty)
documents
- https://www.competefor.com/business/viewOpportunityDetailsSupplier.html?id=42875046 , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/6a6e6b97-f8a3-48f3-874a-e8484f985771 , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 28 Jun 2021 | Award (award) | · | c85333b1-3263-4145-9ef5-fab49787f874-446834 |
more from BMB Joint Venture (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty)
- Thames Tideway Tunnel - C405 Main Works West - Carnwath Road Pit Bottom Steel Alterations · £1 · 5 Jul 2021
- Thames Tideway Tunnel - C405 Main Works West - Intertidal Terrace · £1 · 5 Jul 2021
- Thames Tideway Tunnel - C405 Main Works West - Pipe Jacking works for Syphon Main ACTST · £500,000 · 9 Apr 2021
- Thames Tideway Tunnel - C405 Main Works West - Permanent Formwork Decking · 12 Mar 2021
- Thames Tideway Tunnel - C405 Main Works West - Hammersmith Security Gates & Fencing · £1 · 17 Feb 2021
- Thames Tideway Tunnel - C405 Main Works West - Main Tunnel Steel Connection Shutters · 5 Feb 2021
- Thames Tideway Tunnel - C405 Main Works West - Bulkheads (Acton) · £1 · 8 Jan 2021
- Thames Tideway Tunnel - C405 Main Works West - Hammersmith Connection Culvert Bulkhead · £1 · 21 Oct 2020
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Provision of OSB · The Police, Fire and Crime Commissioner for Northamptonshire
- Provision of OSB · Police, Fire and Crime Commissioner for Northamptonshire · £26,271
- General Timber Materials · East Lothian Council · £225,000
- Oban Pier Upgrades · Northern Lighthouse Board · £250,000
- Natures Wardens - Green Roof Structure · Neath Port Talbot County Borough Council
- Building and Timber · Scottish Borders Council · £78,949
- WEP I Cardiff and Vale College (CaVC) Project Batch: D&B Contract Selection Questionnaire (SQ) · Bouygues UK
- Direct Award of a contract for the provision of Rights of Way & Countryside (RoW&C Team Timber Supplies) · East Sussex County Council · £75,000
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.