Subsea vs Floating Substations - Technoeconomic Comparison - ORE/23/013

Offshore Renewable Energy Catapult Published 24 Oct 2023 Contracts Finder

key details

Value£95,000
Statuscomplete
Category (CPV) 71621000
Deadline30 Nov 2023
Contract start14 Jan 2024
Contract end15 Jan 2025
Procedureopen
SME suitableYes
OCIDocds-b5fd17-4fb30fc0-8629-4f6d-aa4a-9df6d4de52d1

Award

SupplierValueDateStatus
Crondall Energy Consultants £94,744 7 Feb 2024 active

description

The Consultant will be required to define the floating and subsea systems for two case study sites. For consistency, baseline sites from previous FOW CoE projects will be used where possible. Gaps in knowledge and technology will be identified to define a roadmap towards commercial readiness by 2025 to 2030. Experience from previous/ongoing projects will play a key role in this task e.g. previous OREC projects on inter-array cable topology (DC06) and mooring and cable installation (DC07). Key uncertainties in this roadmap should also be defined. A cost comparison should be performed to set out which option would be preferable for a range of potential UK project configurations, subject to a range of assumptions and sensitivities. Finally, a sensitivity of lifetime costs to system reliability levels will be investigated.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

2 notices published against this procurement.

PublishedTypeRegimeNotice
24 Oct 2023 Tender (tender) · b392338f-3b39-4957-9aac-ea686fc74634-691492
21 Feb 2024 Award (award) · 2be66307-be5a-43a0-8d8a-3feb901c0ef0-725212

more from Offshore Renewable Energy Catapult

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.