key details

Value£210,000
Statuscomplete
Category (CPV) 45240000
RegionNorth West
Deadline19 Apr 2019
Contract start10 May 2019
Contract end30 Sept 2019
Procedureopen
SME suitableYes
OCIDocds-b5fd17-407f6988-8f84-4a1e-a7d9-9321dbc1a63e

Award

SupplierValueDateStatus
BAILEY CONTRACTS LTD £214,975 20 Jun 2019 active

description

A contract opportunity for Fish Pass works. The works are to construct a Larinier Super Active Bottom Baffle Fish Pass on the dam structure forming Primrose Lodge and undertaking remedial work to the dam associated with the Fish Pass construction. This is to be achieved through diversion of stream flow into an existing maintenance channel, carrying out remedial works and the construction of the fish pass. The fish pass will be part constructed in-situ and part pre-fabricated and brought to site. The contractor is expected to undertake the engineering design of the fish pass. Details of how to apply are available on the Ribble Rivers Trust website. A link is provided in this notice to the specific pages.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
10 Jul 2019 Award (award) · bd3a083f-875c-4120-a1c0-13062bbb0e80-300564

more from RIBBLE CATCHMENT CONSERVATION TRUST LIMITED

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.