ITT 4109 - 561537 - A46/A1 Western Junction Brownhills - Site Investigations Geotechnical Area 7
key details
| Value | £10,000 |
|---|---|
| Status | active |
| Category (CPV) | 71351500 |
| Region | East Midlands |
| Deadline | 24 Sept 2018 |
| Contract start | 20 Oct 2018 |
| Contract end | 5 Nov 2018 |
| Procedure | limited |
| SME suitable | Yes |
| OCID | ocds-b5fd17-293b7a6d-d35c-478e-8835-5bb3e9f7d86a |
description
Scope of works
Obtain soil samples at location of proposed new ditch alignment. Existing stockpiles within the HE parcel of land need to be tested to ascertain if the material is hazardous.
- The works to be provided under this contract are:
| Category | Survey Description |
| Ground Investigation | Ground Investigation - Samples in accordance with BS 5930:2015 including but not limited to waste classification test including Waste Acceptance Criteria testing |
| 1.3 | Deliverables |
| 1.3.1 | The Contractor is required to produce the following deliverables: |
- the temporary traffic management arrangements provided by the Employer for the use of the Contractor to Provide the Works, including timing and duration.
- the access equipment provided by the Employer for the use of the Contractor to Provide the Works, including timing and duration.
- the temporary accommodation, welfare facilities, services, Plant, Materials and Equipment provided by the Employer for the use of the Contractor to Provide the Works, including timing and duration.
- the starting date and completion date is as stated in the Contract Data.
- the survey is to be undertaken concurrently with other surveys, so the phasing of the traffic management may be dependent on a number of other contractors.
- All works are to be overnight between the hours of 20:00 - 06:00, subject to traffic counts. Works to be completed under traffic management, expected to be slip road closure, ring management, and lane 1 closures.
- Survey results are expected to be received with two weeks of the works being completed on site.
documents
- https://www.contractsfinder.service.gov.uk/Notice/3f3858c2-39d4-46b1-9d2d-6a9e4dbc9491 , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/3eff58b9-e0ca-44ac-a98c-eec4163743a5 , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 13 Sept 2018 | Tender amendment (tenderAmendment) | · | 3f3858c2-39d4-46b1-9d2d-6a9e4dbc9491-240549 |
more from Highways England
- Contract Awarded for Motorway Service Area Energy Storage Systems · £6,561,414 · 15 Feb 2023
- T0399 National Highways Sector Scheme Review · £74,373 · 13 Dec 2022
- Gantries for National Highways · £7,000 · 1 Dec 2022
- T0340 Update of Departures Manual · £39,115 · 25 Nov 2022
- TA SE&E 011 - M27 Junction 10 · £166,004 · 23 Nov 2022
- National Highways Tree/Nurseries Market Engagement · 9 Nov 2022
- A259 Dumb Bell Roundabout - Use Both Lanes traffic survey · £12,000 · 9 Nov 2022
- T0383 TRAS3074 Development of Speed-Emission/Energy Curves and Costs Data for Ultra Low Emission Vehicles · £74,519 · 4 Nov 2022
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- CO Services - LT516 EGL5 Ground Investigation - Multi Site 1126 - Natural Powe · Scottish Hydro Electric Transmission plc
- 715807477 Site Surveys CAN · Ministry of Defence · £131,599
- HPA - Update of Qualitative Risk Assessment, Land Quality Register & Map and APC · Nuclear Restoration Services Ltd · £30,000
- Dungeness A: Boilers Down Groundwater Monitoring Specification · Nuclear Restoration Services Ltd · £15,000
- Ground Investigation Report (GIR) and perform the Overseeing Organisation Geotechnical Advisor (OOGA) role for the Sheepfolds Strategic Drainage project · Sunderland City Council
- East Anglia - (EAN) - CDF Lot 2 - Great Yarmouth Epoch 3 - Early Supplier Engagement (ESE) - OBC-FBC · Defra group Commercial · £56,810
- GI - A303 and M5 7m+ Sign Replacement Tetra Tech · National Highways Limited · £151,846
- MEAS Round Fields Managed Realignment Early Supplier Engagement · Defra · £93,050
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.