Supertram Embedded Rail Replacement Phase 2
key details
| Value | £12,500,000 |
|---|---|
| Status | complete |
| Category (CPV) | 45234116 +1 more |
| Deadline | 8 Dec 2017 |
| Contract start | 1 Oct 2018 |
| Contract end | 1 Dec 2020 |
| Procedure | open |
| SME suitable | No |
| OCID | ocds-b5fd17-19866abc-97a1-4869-8f69-aa96b4e25779 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| VOLKERRAIL LIMITED | £9,340,851 | 18 Apr 2018 | active |
description
The Executive is the owner of the Supertram system. South Yorkshire Supertram Limited (SYSL) (a subsidiary of Stagecoach), operate the Supertram network, and maintain the majority of the asset for the Executive, under a Concession terminated in 2024.
The wear of the embedded rails had reached a condition on certain lengths of the network where it required replacement to prevent the flange of the tram wheels running on the bottom of the rail groove. Accordingly between 2013 and 2015, approximately 15km of embedded rail was replaced. It is proposed to complete the remaining 10km of replacement over the summers of 2018, 2019 and 2020.
The works comprise the replacement of the remaining sections of embedded rail on certain sections of the Sheffield Supertram Network where wear has reached a critical condition. The Executive and South Yorkshire Supertram Limited need to ensure the system remains operable and in order to achieve this, the embedded rails need to be replaced. The works are programmed to run between May 2018 and August 2020.
Additional information: Full tender documentation can be obtained from www.sypte.co.uk/contracts
documents
- https://www.contractsfinder.service.gov.uk/Notice/66f8cffc-559c-40ad-b9af-29ddb9b9f6ae , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 23 Apr 2018 | Award (award) | · | f9b9289f-7965-4123-84c0-46ee100b89ee-212508 |
more from SOUTH YORKSHIRE PASSENGER TRANSPORT EXECUTIVE
- Managed Detection and Response MDR Service · £164,000 · 17 Mar 2026
- Development of a Social Media Strategy · £86,000 · 17 Feb 2026
- Copilot Value Realisation · £59,000 · 13 Oct 2025
- Document Management system · £59,000 · 13 Oct 2025
- SYMCA Plan for Rail · £41,334 · 22 Apr 2025
- Project Management System Configuration · £31,900 · 1 Apr 2025
- Health and Safety Learning and Development Partner · £61,700 · 24 Feb 2025
- Analysis & Reconciliation Services · 6 Feb 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Provision of Priestfield Mitigations LC084 - Phase 1 - Ballast Distribution Works for Midland Metro Limited (MML) · West Midlands Combined Authority
- Rodney Stoke Access Track Improvements · Natural England · £20,833
- Provision of Ballast Storage Area for Midland Metro Limited · WEST MIDLANDS COMBINED AUTHORITY · £34,396
- Provision of Track Baseplate Rectification Works for Midland Metro Limited - The Crescent Tram Stop · WEST MIDLANDS COMBINED AUTHORITY · £287,473
- Provision of Manual Rectification Team for Track Faults for Midland Metro Limited · WEST MIDLANDS COMBINED AUTHORITY · £114,326
- MML Low Level Resurfacing Works - The Crescent Tram Stop · WEST MIDLANDS COMBINED AUTHORITY · £357,896
- MML Rail Ballasted NEC4 Term Service Contract · WEST MIDLANDS COMBINED AUTHORITY · £954,000
- MML Tamping & Geometry Term Service Contract · WEST MIDLANDS COMBINED AUTHORITY · £879,600
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.