Grand Redoubt Gate 1
key details
| Value | £65,338 |
|---|---|
| Status | complete |
| Category (CPV) | 45246000 |
| Region | South East |
| Deadline | 16 Aug 2024 |
| Contract start | 28 Aug 2024 |
| Contract end | 25 Sept 2024 |
| Procedure | selective |
| SME suitable | Yes |
| OCID | ocds-b5fd17-0d3173b1-7c94-461c-9a48-7e85576db65c |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| JT Mackley & Co. Ltd | £65,338 | 27 Aug 2024 | active |
description
ECSC for labour, equipment and materials re: the replacement of one tidal flap within the tidal basin at Redoubt Sluice in Dymchurch (the northern flap). The Contractor shall provide a plastic composite flap of the same size and configuration as the existing flap. The new flap shall be shimmed to permit some leakage, so allowing the passage of elvers upstream. The Contractor shall inspect the southern tidal penstock and suggest remediation to remedy a defect; the flap only opens halfway.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 28 Aug 2024 | Award (award) | · | f2d81cd8-3402-4e14-8d43-1a7d826ff5d5-780894 |
more from Environment Agency
- Blaydon Quarry Landfill Gas Monitoring · £63,233 · 29 Jul 2026
- IMx - Phase 2 · £592,730 · 29 Jul 2026
- YNE AOMR Lot 1 Asset Recon Nunnington Channel Works · £76,486 · 29 Jul 2026
- KSL - Nav - East Farleigh Asset Refurbishment · £7,490,000 · 28 Jul 2026
- EAN - AOMR - East & National Eel Pass Programme · £4,791,694 · 28 Jul 2026
- NW - AOMR - Lot 2 25-27 GMMC MEICA D&B Package · £1,200,000 · 28 Jul 2026
- YOR - CDF - Tidal Ouse Left Bank Saltmarshe - SOC-OBC (ESE) · £64,282 · 28 Jul 2026
- YNE- Stokesley- MMF direct award- 26-27 FY · £74,739 · 28 Jul 2026
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- YNE AOMR Lot 1 Asset Recon Nunnington Channel Works · Environment Agency · £76,486
- YNE AOMR Lot 1 Asset Recon Skerne South Park Fish Pass Renovation · Environment Agency · £46,798
- YNE - AOMR Lot1&3 Incident Response stonbury · Environment Agency · £1
- YNE AOMR Lot 1 Asset Recon Thorpe Marsh - B3 · Environment Agency · £95,592
- YNE AOMR Lot 1 Asset Recon Lowther B Spillway - C15 · Environment Agency · £119,343
- YNE-AOMR Lot 1-North East Area Asset Recon Programme 26 to 27 · Environment Agency · £946,499
- SSD - PFR Scheme Hampshire (Romsey, Otterbourne, etc.) Lot 2 Supply & Install · Environment Agency · £598,522
- LRDS KSL Southern Package 3 - ECI · Defra · £50,000
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.