G4_2_HCC_038 S-TCF Eling to Holbury Cycle Route

HAMPSHIRE COUNTY COUNCIL Published 22 Feb 2023 Contracts Finder
The value below is a framework or dynamic market ceiling: the maximum that could be spent across all call-offs, not the value of a single contract. Aggregate figures on this site exclude these to avoid double counting.

key details

Value£3,441,000
Statuscomplete
Category (CPV) 45230000
RegionSouth East
Deadline18 Nov 2022
Contract start13 Feb 2023
Contract end20 Oct 2023
Procedureselective
SME suitableNo
OCIDocds-b5fd17-2903f29e-fb90-4da4-aeb3-bfd99fff91a5

Award

SupplierValueDateStatus
MILESTONE INFRASTRUCTURE LIMITED £66,117 12 Jan 2023 active

description

A call-off from the Generation 4-TWO 2020 - 2024 Civil Engineering, Highways and Transportation Collaborative Framework (Awarded April 2020).

The scheme is to provide a new cycle route, combining both enhanced shared-use off-road facilities, on-road lanes, improved crossing points. The scheme runs between the Marchwood Road/Bury Lane junction in Eling to the A326 Long Lane / Holbury Drove junction in Holbury, a total distance of over 14km.

This call-off includes Early Contractor Involvement using secondary Option X22 of the NEC4 Engineering and Construction Contract. The works element of the contract will be delivered in Stage Two, within the total £3,441,000 budget.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
22 Feb 2023 Award (award) · e5a838ab-ec01-4413-8390-3ac447c179aa-617593

more from HAMPSHIRE COUNTY COUNCIL

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.