description

The Thames Tideway Tunnel project (the Project) will control CSO discharges by intercepting and diverting combined sewage flows into a new storage and transfer tunnel. The main tunnel will run from Acton Storm Tanks in west London to Abbey Mills Pumping Station in the east, where it will connect to the Lee Tunnel, which will transfer the combined sewage to Beckton Sewage Treatment Works for treatment. The Project extends from Acton Storm Tanks in west London, to Abbey Mills Pumping Station in east London. The Project includes associated works at Beckton STW, Shad Thames Pumping Station and Bekesbourne Street.

The geographic layout of the Project and local authorities through which it passes is shown in Figure 1.

The Project comprises:

  • a.tunnels:
  • i.a main tunnel which will capture and store combined sewage from CSOs along its route and transfer it to Abbey Mills Pumping Station, from where the Lee Tunnel will transfer it for treatment at Beckton Sewage Treatment Works
  • ii.11 connection tunnels, which will link flows from CSOs to the main tunnel.
  • b.Worksites:
  • i.five main tunnel Worksites (drive and/or reception sites)
  • ii.16 CSO Worksites
  • iii.two System modification Worksites Thames Tideway Tunnel
  • iv.works at Beckton Sewage Treatment works.

Scope of Works

Complete remaining secant piles

Local excavation and break back piles to expose the reinforcement Design, Supply and Install of formwork to capping beam Cast capping beam to levels indicated in drawing 3320-AAJV-CARRR-540-SZ-DR-000005 below to act as waling beams including couplers for internal walls and slab where required.

Design, Supply and Install temporary props in accordance with temporary works drawings provided Excavation to +98.100mATD

Install the dowel bars into the male piles.

Design, Supply and Install Formwork for RC base slab - sumps and upstands Cast RC base slab

Design, Supply and Install Formwork for RC liner walls Cast RC liner walls

Design, Supply and Install Formwork for RC internal walls and beams Cast all RC internal walls and beams

Design, Supply and Install Formwork for slab at ground level Cast 3.8m width slab at ground level

Removal of temporary props

Design, Supply and Install of falsework to cast top slab Fill pocket of RC internal wall

Pour top slab in stages as agreed with the Contractor Striking of falsework

Design, Supply and Install of formwork to top slab upstands.

Returned quotations will be evaluated by BMB JV's (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty) Procurement team in conjunction with our design and engineering teams.

Quotations will be evaluated based on;

Cost

Timeliness of return

Adherence to and demonstration of understanding of the drawings and specifications provided at this point.

Provision of accurate product specifications to accompany the quotation.

Su

Additional information: Carnwath Road Riverside Site - SW6 3HR

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
3 Mar 2022 Award (award) · 49525da7-79c8-4e99-b3f9-2625e9eac7dc-513602

more from BIP SOLUTIONS LIMITED

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.