Call off - Lot 13 - Revised - Review of the Mersey Tunnel Toll Setting Process - Economic Impacts

Merseytravel Published 18 Nov 2016 Contracts Finder

key details

Value£27,321
Statuscomplete
Category (CPV) 71310000
RegionNorth West
Deadline8 Sept 2015
Contract start5 Oct 2015
Contract end27 Nov 2015
SME suitableNo
OCIDocds-b5fd17-f1b735a1-adc9-11e6-9901-0019b9f3037b

Award

SupplierValueDateStatus
Mott MacDonald Ltd £27,321 21 Sept 2015 active

description

Call-off from Merseytravel Consultancy Services Framework. Lot 13 - Business Case Development

The Mersey Tunnels toll setting process is currently governed by the County of Merseyside Act (1980) as amended by the Tunnels Act 2004.

During the formal toll setting process in February 2015, the Combined Authority passed the following resolution:

“a task group be set up to consider options open to the Combined Authority to reduce the costs of tunnel tolls and its impact in infrastructure and transportation”

There was also a wider decision relating to a review of the Mersey Tunnel Act in any on-going devolution negotiations under minute 79 (iv), but this work is out of scope of this task group and should continue separately.

The key purpose of this commission is to inform this task group, once formally established, of the economic and social impacts of the Mersey Tunnels for the Liverpool City Region as a whole.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
18 Nov 2016 Award (award) · 61deedf6-43ea-412d-bda7-8c77fc4b6940-103878

more from Merseytravel

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.