The value below is a framework or dynamic market ceiling: the maximum that could be spent across all call-offs, not the value of a single contract. Aggregate figures on this site exclude these to avoid double counting.

key details

Value£215,797
Statuscomplete
Category (CPV) 73000000
Deadline30 Oct 2018
Contract start7 Feb 2019
Contract end31 Mar 2019
Procedureselective
SME suitableNo
OCIDocds-b5fd17-dc55347c-9376-4132-9db0-1706003543e8

Award

SupplierValueDateStatus
Ove Arup £215,798 7 Feb 2019 active

description

As per the original work package 383, the full range of PCF products will be required for all schemes, and Highways England has provided new guidance on this for these smart motorway schemes. The new PCF products are:

  • Package-specific reduced Appraisal Specification Report setting out ADDITIONAL tasks to be undertaken following the initial review of the quality of the source model in the area defined by the likely region of impact (LRoI) of the smart motorways, with an associated work programme;
  • ComMA Report (which will combine the Traffic Data Collection Report, Local Model Validation Report, Traffic Forecasting Report and Economic Assessment Report into one document)
  • An AST is required for each scheme (NOT PACKAGE), completed to the appropriate level of detail from modelling outputs, although the primary owner of the AST will be the Lot 1 Design team; and
  • Other traffic related inputs to the Business Case and/or Wider Benefits.

Additionally, direct model outputs are now recognised as specific PCF products, namely:

  • Calibrated/validated base year traffic model outputs;
  • Forecast traffic model outputs suitable to inform scheme design and environmental modelling; and
  • Economic appraisal results.

The forecast traffic flow and speed data to inform environmental modelling will include detailed speed banding information.

At the conclusion of the package order, a Handover Report will be required, to include a lessons learnt log and feedback to the RTM Maintenance team such as improvements to the network/zoning, and any new practices developed. This report should also detail the structure and naming of the final model files, which are themselves to be supplied on appropriate media (e.g. DVDs, external hard drive, etc.) alongside the report. The report should be sufficiently detailed to allow a third party to understand and run the model with no additional information.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
21 Feb 2019 Award (award) · d46864f4-7127-4dd1-badc-b5e44488e412-271347

more from Highways England

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.