Supply Chain notice: SYS0151 & SYS0152 - Penstock replacements design and build Portsmouth Naval Base (D Lock & North Pump Penstocks)
key details
| Value | £8,000,000 |
|---|---|
| Status | active |
| Category (CPV) | 42131220 |
| Region | South East |
| Deadline | 31 Dec 2023 |
| Contract start | 1 May 2024 |
| Contract end | 30 Jun 2025 |
| Procedure | selective |
| SME suitable | Yes |
| OCID | ocds-b5fd17-b30ee31c-1afd-400e-a542-3522b8559921 |
description
The Tenderer should be aware that the works detailed in this package are constrained due to the nature of the location they are to be conducted in.
Project location
HM Naval Base Portsmouth
The Contractor shall be expected to adhere by the HMNB site security requirements, all Contractors and Sub-Contractors shall be BPSS security vetted and will be required to hold the relevant site security passes.
The Contractor shall be expected to hold the following levels of insurance £10m Public Liability, £10m Product Liability, £5m Professional Indemnity.
KBS Maritime - Introduction
KBS Maritime is a joint venture between KBR and BAE Systems, bringing together two global players with a rich heritage of delivering excellence, innovation and reliability. The joint venture will combine the expertise of KBR as a global leader in infrastructure asset management and services with BAE Systems' experience and capability within Portsmouth Naval Base. KBS Maritime are delivering an ambitious, modern and enduring change to the Portsmouth Naval base infrastructure, securing investment in the local community and ensuring fit-for-purpose, world-leading fleet support for the Royal Navy and the UK in the decades ahead.
Project Background
KBS Maritime have a requirement for a programme of 8 penstock replacements at D Lock (project number: SYS0151-01) over the next year. The penstocks will vary in duty, with pressures ranging from 6mWC to 22mWC, both on and off head. Penstocks shall be manufactured to BS7775, feature non-rising spindles and electric actuation. The successful tenderer shall be able to demonstrate experience in removing existing penstocks, designing, installing and commissioning new penstocks suitable for use in seawater.
KBS Maritime also have a requirement for a programme of 11 penstock replacements at North Pumping Station (project number: SYS0152-01) over the next year. The penstocks will vary in duty, with pressures ranging from 6mWC to 22mWC, both on and off head. Penstocks shall be manufactured to BS7775, feature non-rising spindles and electric actuation. The successful tenderer shall be able to demonstrate experience in removing existing penstocks, designing, installing and commissioning new penstocks suitable for use in seawater.
KBS will then have a rolling programme of 40+ penstocks to be replaced from FY24/25 to beyond 2030. The penstocks will vary in duty, with pressures ranging from 6mWC to 22mWC, both on and off head. Penstocks shall be manufactured to BS7775, feature non-rising spindles and electric actuation. The successful tenderer shall be able to demonstrate experience in removing existing penstocks, designing, installing and commissioning new penstocks suitable for use in seawater.
Additional information:
Contractor SQEP (Suitably Qualified and Experienced Personnel) guidance
Industry track record, confined space working, salt water environments, large and deep wells, working within MoD establishments. NIC EIC approved (National Inspection Council for Electrical Installation Contracting), NACE accreditation, EN1090 execution class 3., Achillies UVDB, City & Guilds confined space level 2/3 for operatives, level 5 for managers, Welder quals to BS EN 287, Security clearance, IPAF (International Powered Access Federation), SMSTS (Site Management Safety Training Scheme), IOSH (Institution of Occupational Safety and Health), NEBOSH (National Examination Board in Occupational Safety and Health), CHAS (Contractors Health and Safety Assessment Scheme), Safe Contractor.
Key Dates (approximate)
Expressions of Interest: 31 December 2023
ITT Published: Late January 2024
ITT Close: Mid/Late March 2024
Construction commencement: 01 May 2024
Project Completion : 30 June 2025
: If you are interested in this opportunity, please contact Chris May - at Tenders@kbsmaritime.com to express interest. quoting ref SYS0151 & SYS0152 - Penstock replacements design and build Portsmouth Naval Base (D Lock & North Pump Penstocks).
Once the notice has closed, suppliers will be invited to Pre-Qualify and/or Invited to Tender. Open or restricted tender procedure will be dependent on the number of expressions of interest received. A Non-Disclosure Agreement will also be required, prior to participating in a Pre Qualification and/or Invitation to Tender.
documents
- https://www.contractsfinder.service.gov.uk/Notice/4e8e2a71-99f5-4f9a-8e92-63fc3be92fa8 , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 23 Nov 2023 | Tender (tender) | · | 4e8e2a71-99f5-4f9a-8e92-63fc3be92fa8-701152 |
more from Ministry of Defence
- TTHC/0017 Torpedoes Repair and Maintenance (TRAM) · £405,762,737 · 29 Jul 2026
- 713107450 In Service Support of Type 45, Integrated Navigation and Bridge System Award notice · £9,888,089 · 28 Jul 2026
- SUPPLY CHAIN NOTICE - Calibration Services For Tooling Supporting Boeing, Vertical Lift Helicopters. · £12,000 · 28 Jul 2026
- SUPPLY CHAIN NOTICE - WC1996767 - (MT0019, MT0106, MT0265, MT0494) - Remedial works required to M&T Structures from the PAs, Akrotiri & Dhekelia, CYPRUS · 28 Jul 2026
- 715878489 - MCF 4 Order Form · £1,082,000 · 28 Jul 2026
- Provision of Foreign Currency SUpply to 2028 · £800,000,000 · 28 Jul 2026
- 704461451-MSS/141-SPA707 - CAN · £1 · 28 Jul 2026
- External Legal Support for FMSP Extensions · £450,000 · 27 Jul 2026
all contracts from this buyer →
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.