Shooters Grove Accessibility Phase 2
key details
| Value | £150,000 |
|---|---|
| Status | complete |
| Category (CPV) | 45214200 |
| Region | Yorkshire and the Humber |
| Deadline | 8 Nov 2021 |
| Contract start | 7 Mar 2022 |
| Contract end | 27 May 2022 |
| Procedure | selective |
| SME suitable | Yes |
| OCID | ocds-b5fd17-ac4775a3-18f9-47f0-bd03-413d9918796a |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| R H Fullwood & Co Ltd | £259,441 | 3 Feb 2022 | active |
description
The project is the construction of a new extension to house a Hygiene Room and Lobby, installation of a platform lift, alterations to existing toilets and external works.
The Works to the Extension comprise: excavations, foundations and floor slab, brick / block walls, timber flat roof, doors, windows, fittings, finishings, services and decoration.
The Works to the Lift comprise: forming opening in existing external wall, excavations and foundations to pit, new platform lift and shaft, structural supports, new window and services.
The Works to the existing Toilets comprise: removing fittings and partitions, new partitions, windows, sanitary fittings, finishings, services and decoration.
The Works to External Areas comprise: demolitions, new retaining wall, fencing, paving, car parking and drainage works including new pipe runs and manhole.
Some of the works are required to be completed during the school holidays (see Pre-Construction Information within Appendix F of the Tender Documents. The remainder of the works will be completed during the school term time when the building is fully functioning and occupied. Therefore, all areas of work must be made clear and segregated from occupied areas to ensure no access to the works is possible by any building user.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 11 Feb 2022 | Award (award) | · | 20809132-f159-4d30-b87d-f745f799ffc7-509545 |
more from Sheffield City Council
- ECM ENDCLIFFE PARK RIVER WALLS · £326,855 · 23 Jul 2026
- HOUSING LEGIONELLA RISK ASSESSMENTS - TERM CONTRACT 2026-2029 · £69,237 · 23 Jul 2026
- ATHELSTAN PRIMARY SCHOOL TEMPORARY CLASSROOMS · £797,493 · 2 Jul 2026
- PRIVATE SECTOR HOUSING - PROVISION OF STAIRLIFTS AND ASSOCIATED WORKS 2026-2029 · £900,000 · 23 Apr 2026
- MEDIUM RISE COMMUNAL FIRE DOOR INSPECTIONS · £114,978 · 19 Mar 2026
- COUNCIL HOUSING ADAPTATIONS WORKS PROGRAMME 2026-29 · £8,904,560 · 5 Mar 2026
- ABBEYDALE DAM LEAKS · £1,316,453 · 6 Nov 2025
- FORGE DAM LEAKING SLUICE GATE - DESIGN · £22,722 · 9 Oct 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Flagship SEN School -Main Works (con_31833) · Department for Education · £3,540,678
- River Tees Academy - Main Works (con_31827) · Department for Education · £20,792,548
- Wellfield Academy - Main Works (con_31815) · Department for Education · £44,887,810
- Europa School UK - Main Works (con_31805) · Department for Education · £8,366,969
- Anglo European School - Main Works (con_31751) · Department for Education · £53,313,769
- Sacred Heart Catholic Primary School - Main Works (con_31749) · Department for Education · £1,034,254
- Kepier - Extension · EDEN LEARNING TRUST · £6,000,000
- Bedford High School - Bistro/Kitchen Roof Replacement · Wigan Council · £186,869
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.