gvtcx

SDF Lot 2 South East_ Tilbury Douglas A

Highways England Published 29 Jul 2022 Contracts Finder

key details

Value£22,753,920
Statuscomplete
Category (CPV) 45000000
RegionSouth East
Deadline8 Mar 2021
Contract start27 May 2022
Contract end31 Aug 2027
Procedureselective
SME suitableYes
OCIDocds-b5fd17-a14fe222-811f-4cbe-a6b8-2758f7c358f6

Awards (2)

This procurement was awarded to 1 suppliers. Values shown are per-award; the notice total is £22,753,920.

SupplierValueDateStatus
Tilbury Douglas Construction Ltd £22,753,920 26 May 2022 active
Tilbury Douglas Construction Ltd · · active

description

National Highways continues to roll out the Asset Delivery model to its operational areas. There is a requirement to deliver a range of renewal, improvement and selected small scheme construction works on the Strategic Road Network in areas utilising specialist contractors working collaboratively with National Highways to deliver these works. It is envisaged that this framework will straddle two Road Investment Strategy (RIS) periods (RIS 2 and RIS 3) enabling a smooth transition between them. Works for schemes have been divided into a number of workstreams that align with the contractors' specialisms, and will also include design.

Bandings have been introduced into the framework model to differentiate some contracting terms between bands.

This award is for Lot 2 Drainage in the South East region (National Highways Areas 3 and 4).

This Lot covers the supply of materials, plant and labour to carry out;

  • Construction, commissioning and removal of drainage and manhole/catch pits,
  • Renewal or recycling of filter drain material,
  • Renewal and repair of pipes and pipe lining,
  • Renewal of ditches, swales, ponds and any other vegetative treatment systems,
  • Control and disposal of contaminated material,
  • Installation, commissioning and removal and renewal of flow control equipment, and
  • Installation, commissioning and removal and renewal of any other drainage ancillary items including petrol interceptors and pumping station equipment

Other duties This scope also includes:

  • Mobilisation
  • Early Contractor Involvement
  • Principal contractor
  • Welfare facilities
  • Manage Network Occupancy
  • Community; and
  • Contingency

The scope may also include carrying out some of the duties of the Maintenance & Response Contractor and providing Incident Response (Rapid Response) when instructed.

notice history

2 notices published against this procurement.

PublishedTypeRegimeNotice
29 Jul 2022 Contract award notice (F03) Earlier regulations 020833-2022
29 Jul 2022 Award (award) · f0640264-4b9e-409a-9147-e777aad02470-559029

more from Highways England

all contracts from this buyer →

similar contracts awarded