C0024 Smart Motorways Audit Service
key details
| Value | £366,724 |
|---|---|
| Status | complete |
| Category (CPV) | 71242000 |
| Region | London |
| Deadline | 18 Aug 2023 |
| Contract start | 21 Aug 2023 |
| Contract end | 31 Aug 2024 |
| Procedure | selective |
| SME suitable | No |
| OCID | ocds-b5fd17-0ed62317-e9b0-442c-b58f-d882ecad707f |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| Arcadis | £366,724 | 20 Aug 2023 | active |
description
Working in conjunction with the Alliance Commercial Assurance Lead and the Client SMPA Commercial Lead (Service Manager), the consultant will be expected to;
- oDevelop, lead and manage the implementation of an Alliance Defined Cost audit regime including Lot 1, 2 and 3 Partners along with associated Client Costs across Performance Period 4 (April 2023- March 2024). As a minimum, the regime should confirm that;
- oDefined Cost have been properly incurred in providing the works and is allowable in accordance with the Alliance contract.
- oA robust audit trail of accounts and exists to support the Alliance and Client Costs.
- oEvidence exists that the invoiced cost has been paid in full without the application of discounts or rebates.
- oEnsure annual performance statement to the Client on performance is robust and supported by evidence those performance levels have been achieved.
- oEnsure Goals payment amounts are correctly applied in accordance with the Implementation Plan
- oEnsure Budget performance is correctly reflected in accordance with the Contract
With support with the Procurement and Supply chain team and Lot 3 Partners, develop and deliver an audit regime to ensure subcontract cost have been properly assessed in accordance with various subcontract forms and that Alliance procurement processes have been complied with.
Support Lot 3 Partners develop and deliver an audit regime for subcontractors Defined Cost incurred in relation to cost-based subcontracts forms.
Support the Alliance commercial team proving interim cost assurance for Application for Payments.
Periodic verification of cost allocation at a scheme level to ensure costs are allocated correctly within the Cost Breakdown Structure.
Periodic provision of unit cost data in accordance with the Clients Commodity Breakdown Structure.
Deliver the annual audit and interim account regime for each Performance Period under the Alliance contract. Note - this should be largely based on progressive delivery of service across the Performance Period.
Support the Client in delivering an assurance regime of Client Costs.
At regular intervals (no greater than three months), provide to the Alliance Manager a detailed report identifying the nature and extent of costs audited to date, any issues identified, current status and the quantum of any resultant adjustments to the account.
Ensure robust records are maintained by the Partners including providing support where required to ensure a minimum standard to record keeping is achieved across the Alliance.
Supporting the Alliance Commercial Assurance Lead to continue to develop the broader Alliance commercial assurance regime including defining and managing resource requirements.
Ensure adherence to the SMP Alliance contract in the production of Earned Value Measurement by the assurance of the Primavera P6 schedules issued by the Alliance Team, along with the associated documentation that supports those schedules. In order that the National Highways
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 24 Aug 2023 | Award (award) | · | 8ca0fe8e-bedf-42c8-89b1-e364d1956a99-674913 |
more from National Highways
- PDF - Framework - A120 Horsley Cross - Parkeston Rbt Harwich Safety Impt · £28,022 · 28 Nov 2025
- PDF Framework - A27 Falmer Footbridge Headroom · £2,390 · 28 Nov 2025
- PDF Framework - RM1016 Holyport interchange · £11,909 · 28 Nov 2025
- PDF Framework - A5 EB WB M42 J10 - A5148 Wall SCRIM · £302,105 · 28 Nov 2025
- PDF Framework - A23 S Downs Way, Hickstead, Pyecombe Bundle - SDF Part 2 & 3 · £3,921,468 · 28 Nov 2025
- PDF Framework - A63 Brighton Street to Daltry Street Resurfacing · £555,028 · 28 Nov 2025
- PDF Framework - M6 J9 SB & NB Bescot Viaduct Pavement Hybrid Group 43 · £40,084 · 28 Nov 2025
- GI - BAM A38 signing · £43,972 · 28 Nov 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- GB-Newcastle upon Tyne: Cost Manager and Contract Administrator · Northumbria University · £49,426
- Cost Estimating Framework · National Highways Limited · £12,000,000
- Construction Professional Services Delivery-Cost Management-Contract Award-Reserve Contractor · Home Office
- Construction Professional Services Delivery-Cost Management-Contract Award-Main Contractor · Home Office · £600,000
- Construction Professional Services Delivery-Multi Disciplinary Team-Awarded Contract-Reserve · Home Office
- Construction Professional Services Delivery-Multi Disciplinary Team-Awarded Contract-Main Contractor · Home Office · £57,000,000
- Cost Estimating Framework - Task Order - CEF04 Package 3 - Cumming Group FY 26/27 · National Highways Limited · £200,000
- Multi-Storey Car Park Review · Suffolk Coastal District Council and Waveney District Council · £61,400
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.