gvtcx

Thames Tideway Tunnel - C405 Main Works West - Acton Storm Tanks, Ducting Works

BIP SOLUTIONS LIMITED Published 15 Aug 2019 Contracts Finder

key details

Statuscomplete
Category (CPV) 44163110 +2 more
RegionLondon
Deadline23 Aug 2019
Contract start30 Sept 2019
Contract end22 Nov 2019
Procedureopen
SME suitableNo
OCIDocds-b5fd17-8f2df4ea-cd32-4ebe-b311-7f57aa546e7c

Award

SupplierValueDateStatus
not named £419,198 21 Jan 2020 active

description

The Thames Tideway Tunnel project (the Project) will control CSO discharges by intercepting and diverting combined sewage flows into a new storage and transfer tunnel. The main tunnel will run from Acton Storm Tanks in west London to Abbey Mills Pumping Station in the east, where it will connect to the Lee Tunnel, which will transfer the combined sewage to Beckton Sewage Treatment Works for treatment. The Project extends from Acton Storm Tanks in west London, to Abbey Mills Pumping Station in east London. The Project includes associated works at Beckton STW, Shad Thames Pumping Station and Bekesbourne Street.

The geographic layout of the Project and local authorities through which it passes is shown in Figure 1.

The Project comprises:

  • a.tunnels:
  • i.a main tunnel which will capture and store combined sewage from CSOs along its route and transfer it to Abbey Mills Pumping Station, from where the Lee Tunnel will transfer it for treatment at Beckton Sewage Treatment Works
  • ii.11 connection tunnels, which will link flows from CSOs to the main tunnel.
  • b.Worksites:
  • i.five main tunnel Worksites (drive and/or reception sites)
  • ii.16 CSO Worksites
  • iii.two System modification Worksites Thames Tideway Tunnel
  • iv.works at Beckton Sewage Treatment works.

The Main Works West - Contract 405: all works from and including the Acton Storm Tanks shaft to and including the Carnwath Road Riverside shaft, as well as the Frogmore connection tunnel from Carnwath Road Riverside shaft to King George's Park shaft.

This works package is for the supply and installation of Condensate drains, Air Ventilation ducts and MEICA ducts, throughout the Acton Storm Tanks TTT West site.

Supply and installation of the following:-

Acton Storm Tanks, Ducting Works as shown on the attached drawings.

Returned quotations will be evaluated by BMB JV's (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty) Procurement team in conjunction with our design and engineering teams.

Quotations will be evaluated based on;

Cost

Timeliness of return

Adherence to and demonstration of understanding of the drawings and specifications provided at this point.

Provision of accurate product specifications to accompany the quotation.

Supplier experience of similar projects,evidence of this will be requested should the initial quotation be of interest.

Should the candidate supplier be shortlisted they will then be contacted directly by a member of the BMB Procurement Team within two weeks of shortlisting to discuss the requirement in detail.

BMB Joint Venture (BAM Nuttall, Morgan Sindall PLC & Balfour Beatty)

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

more from BIP SOLUTIONS LIMITED

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.