Attenuation Precast Tanks
key details
| Value | £1,000,000 |
|---|---|
| Status | active |
| Category (CPV) | 51810000 |
| Region | London |
| Deadline | 11 Sept 2025 |
| Contract start | 27 Mar 2026 |
| Contract end | 26 Mar 2027 |
| SME suitable | No |
| OCID | ocds-b5fd17-8a01bc23-ff2c-4fa2-9ab8-3e551d2028bc |
description
Kilnbridge have secured the HS2 Old Oak Common Station Works Package for the construction of Urban Realm elements and the Head Houses and Ancillary Buildings. Part of these works require the installation of two, precast concrete attenuation tanks to the eastern part of the site. These tanks are a Subcontractor's design portion.
| Eastern HS2 Attenuation Tank | ||
| • | Area | 1115m2 |
| • | Volume | 1165m3 |
| • | Tank Depth | 1.1m |
| • | Void Ratio | 0.95 |
| Eastern HS2 Dirty Water Tank | ||
| • | Area | 1115m2 |
| • | Volume | 350m3 |
| • | Tank Depth | 1.6m |
| • | Void Ratio | 0.95 |
Kilnbridge are seeking the services of suitably qualified and experienced Sub-subcontractor who shall be responsible for developing the Contractors Detailed Design to Design for Construction & Manufacturing. Taking from RIBA 4 to RIBA 5 stage. The Sub-subcontractor shall be responsible for providing their own design and design for construction drawings, compliant with the design intent of the Contractors Designer.
The Sub-subcontractor will be responsible for ensuring the submission and acceptance of their design from the Contractor and Contractor's design consultant through the Subcontractor.
Works include the design , manufacture and supply of precast base, walls and roof units to site. Scope to include for, but not limited to, technical assurance, BIM modelling, asset scheduling and labelling, drawings for approval, as built drawings, indicative construction sequence methodology, submission of design packs, material approvals, and sustainability and environmental management.
Sub-subcontractor to interface their design with incoming services as detailed on the construction drawings.
Construction is currently forecasted to be carried Q2 2026
documents
- https://www.contractsfinder.service.gov.uk/Notice/9c4a1667-7de9-41c2-8bab-b93f9f148938 , tenderNotice
- https://www.competefor.com/business/viewOpportunityDetailsSupplier.html?id=99297024 , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 4 Sept 2025 | Tender (tender) | · | 9c4a1667-7de9-41c2-8bab-b93f9f148938-862252 |
more from Kilnbridge Construction Services Ltd
- CBGM Installation - KCSL · £250,000 · 6 Jan 2026
- Vehicle Restraint Barriers C4-KCSL · £100,000 · 8 Jul 2025
- Fit-Out Package C4-KCSL copy · £10,000,000 · 3 Apr 2025
- Fit- out C4 -KCSL · £100,000 · 13 Mar 2025
- Screeding C4-KCSL · £1,000,000 · 13 Feb 2025
- Spray Waterproofing C4-KCSL · £150,000 · 28 Jan 2025
- Material Testing, Environmental Engineer Geo Tech - C4- KCSL · £1,000,000 · 28 Jan 2025
- Utilities C4 - KCSL · £1,000,000 · 12 Nov 2024
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.