key details

Value£50,000
Statusactive
Category (CPV) 50800000
Deadline16 Sept 2024
Contract start30 Sept 2024
Contract end31 Oct 2024
Procedurelimited
SME suitableYes
OCIDocds-b5fd17-6abadfd2-1842-4966-a901-8cec16cfaab9

description

The Priory is a listed building. We have a small passenger and goods lift capacity for 6 persons and a maximum load of 450 kg that is used from the ground floor to get to the first floor. We also have a motor room to the side of the lift. The lift is all most 30 years old and is in need of complete upgrade. All tenders will need to do a complete site survey to be arranged with the maintenance manager before putting in a tender. Tender to come with maintenance contract costs.

Access and possible restrictions in the delivery phase of the project.Access to the priory is from 8 to 5 every week day. Weekend work can be arranged with maintenance manager if there is no events on.
Progress reportingThe council will require reporting as required and in particular any impact on the project timescale, plus anything that may cause reputational damage to the council.
Payment termsPlease specify in the pricing schedule the requirement for any phased payments. WTC seek to pay all correct invoices within 30days.
Retention value / periodWTC will retain 0% of the contract value for a period of X months.
Penalty clausesClause to be inserted as required.
Conditions of contractThe Council require assurances from all potential contractors through the provision of appropriate documentation that:
All operatives are suitably trained and qualified to use any machinery involved in the work.
Operatives will at all times wear suitable protective clothing and high viz jackets.
Safety and advisory signage will be required as necessary
Contractors will be required to supply details of public liability insurance with the tender papers.
Contractors will be required to undertake a COSHH assessment for all chemicals used during the delivery of the contract.
Contractors will be expected to provide a method statement detailing how the various elements of the work will be undertaken.
Project timescales will be provided where applicable.
Access and possible restrictions in the delivery phase of the project.Access to the priory is from 8 to 5 every week day. Weekend work can be arranged with maintenance manager if there is no events on.
Progress reportingThe council will require reporting as required and in particular any impact on the project timescale, plus anything that may cause reputational damage to the council.
Payment termsPlease specify in the pricing schedule the requirement for any phased payments. WTC seek to pay all correct invoices within 30days.
Retention value / periodWTC will retain 0% of the contract value for a period of X months.
Penalty clausesClause to be inserted as required.
Conditions of contractThe Council require assurances from all potential contractors through the provision of appropriate documentation that:
All operatives are suitably trained and qualified to use any machinery involved in the work.
  • Operatives will at all times wear suitable protective clothing and high viz jackets.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
11 Jul 2024 Tender (tender) · 199dc5af-467a-466f-990f-0dd7a7934f18-766393

more from Ware Town Council

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.