gvtcx

BBV HS2 MWCC North - Delta - Precast Segmental Viaduc - SIDE SPAN TRUSSES

BIP SOLUTIONS LIMITED Published 23 Dec 2021 Contracts Finder

key details

Value£1
Statuscomplete
Category (CPV) 45223100 +2 more
RegionWest Midlands
Deadline7 Jan 2022
Contract start27 May 2022
Contract end29 Sept 2023
Procedureopen
SME suitableYes
OCIDocds-b5fd17-6456d241-7ea2-4ad0-ab9b-2ffd195f3e58

Award

SupplierValueDateStatus
not named £2,110,029 28 Nov 2022 active

description

Balfour Beatty VINCI (BBV) have been awarded HS2 main works civils contracts, lots N1 and N2 under an Early Contractor Involvement contract (ECI). We are currently in stage two of the process.

We are looking to engage with supply chain who provide Design, supply and commissioning of the Side Span Trusses.

Full details and specifications will be provided to the successfully shortlisted suppliers. Suppliers should be aware of the scale of this project and should assess their internal capabilities to be able to carry out the intended scope of works, prior to completing this expression of interest (EOI).

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
30 Nov 2022 Award (award) · ed6af79b-01a4-4618-9246-677ab829d800-593772

more from BIP SOLUTIONS LIMITED

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.