Thames Tideway Tunnel - C405 Main Works West - Project wide Access Covers

BIP SOLUTIONS LIMITED Published 15 Jun 2021 Contracts Finder

key details

Value£51,000
Statuscomplete
Category (CPV) 44423760
RegionLondon
Deadline18 Jun 2021
Contract start23 Jul 2021
Contract end1 Aug 2023
Procedurelimited
SME suitableNo
OCIDocds-b5fd17-575166de-8df2-485a-969d-4405ab1cf94a

Award

SupplierValueDateStatus
not named £61,441 18 Sept 2021 active

description

The Thames Tideway Tunnel project (the Project) will control CSO discharges by intercepting and diverting combined sewage flows into a new storage and transfer tunnel. The main tunnel will run from Acton Storm Tanks in west London to Abbey Mills Pumping Station in the east, where it will connect to the Lee Tunnel, which will transfer the combined sewage to Beckton Sewage Treatment Works for treatment. The Project extends from Acton Storm Tanks in west London, to Abbey Mills Pumping Station in east London. The Project includes associated works at Beckton STW, Shad Thames Pumping Station and Bekesbourne Street.

The geographic layout of the Project and local authorities through which it passes is shown in Figure 1.

The Project comprises:

  • a.tunnels:
  • i.a main tunnel which will capture and store combined sewage from CSOs along its route and transfer it to Abbey Mills Pumping Station, from where the Lee Tunnel will transfer it for treatment at Beckton Sewage Treatment Works
  • ii.11 connection tunnels, which will link flows from CSOs to the main tunnel.
  • b.Worksites:
  • i.five main tunnel Worksites (drive and/or reception sites)
  • ii.16 CSO Worksites
  • iii.two System modification Worksites Thames Tideway Tunnel
  • iv.works at Beckton Sewage Treatment works.

Scope of Works

The scope is for the supply of Stainless Steel, Galvanized & Ductile Iron Access Covers as detailed in TTW - Access Covers Specification Extracts v2 and Access Covers Procurement Schedule v3 together with all documents and specifications listed within this Invitation To Tender. The Access Covers will be required for our Carnwath Road, Putney, Acton, King Georges Park and Barn Elms Worksites.

Technical Responses

Provide all materials technical data sheets
Provide details of all accreditations
Provide details of production lead time and availability.
Supply of COSHH data sheets for all products
Material Compliance Record's shall be required for all materials where applicable
To comply with the relevant provisions of BS EN 124, BS 7903 and the Highway Agency's 'Chamber Tops and Gully Tops for Road Drainage and Services: Installation and Maintenance' HA 104/09 (or CD534). See Specification for further details.
Where cover size indicated is not a standard sizing, alternative sizing may be suggested and noted by the supplier.
Standard lockable option to be proposed by supplier. Locking mechanism to be advised by supplier.
See specification for further requirements. Galvanised covers and frames shall comply with the relevant provisions of BS EN ISO 1461.
All covers shall have standard 'T' lifting keys or threaded. Supplier to advise the diameter of threaded keys.
Method of lifting covers to be advised by supplier including indicative weights.

Commercial Response

Additional information: Acton Storm Tanks Worksite

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
17 Nov 2021 Award (award) · 2ccbae27-e02a-480f-ab11-b520cfad680e-486259

more from BIP SOLUTIONS LIMITED

all contracts from this buyer →

source

Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.