EPC Contractor for 40-60MW hydropower plant in Zambia
key details
| Value | £145,000,000 |
|---|---|
| Status | active |
| Category (CPV) | 09310000 +3 more |
| Deadline | 26 Feb 2016 |
| Contract start | 31 Mar 2017 |
| Contract end | 31 Mar 2020 |
| SME suitable | No |
| OCID | ocds-b5fd17-3b9b2074-adc9-11e6-9901-0019b9f3037b |
description
Seeking a contractor with the relevant experience and capacity (either together with sub-contractors or in a consortium) for the engineering, procurement and construction (EPC) contract for the design, manufacture, supply, assembly, testing, delivery, installation, commissioning and inter-connection of an expected 40 – 60 MW run of river hydro-electric power plant in rural Zambia.
The EPC contract will be a fixed price, date-certain, full turnkey wrap contract based on FIDIC Silver Book.
Additional information: This procurement is being carried out in accordance with the UK Public Contracts Regulations 2015 (the “Regulations”) which implements EU Directive 2014/24/EU, using the competitive dialogue procedure under Reg 30.
The Ngonye Falls Hydro-power Project, in the Western Province of Zambia, is being developed by Western Power Company Limited, a Zambian company, and InfraCo Africa Limited through its principal project developer eleQtra Limited. InfraCo Africa is a multi-government, donor-funded, privately managed company providing early stage development capital and expertise to develop infrastructure projects in sub-Saharan Africa. The sole shareholder and funder of InfraCo Africa is the Private Infrastructure Development Group (PIDG). Entities that the PIDG has established or funds are required to comply substantially with and in the spirit of EU Procurement laws.
documents
- https://www.contractsfinder.service.gov.uk/Notice/abd5dd32-17a1-4664-9e9c-54d12ad41013 , tenderNotice
- https://www.contractsfinder.service.gov.uk/Notice/Attachment/ad6a87ca-8602-413e-a3b8-8c5b0da6c4bf , application/pdf
- http://www.westernpower.org , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 18 Nov 2016 | Tender (tender) | · | abd5dd32-17a1-4664-9e9c-54d12ad41013-85533 |
more from ELEQTRA LIMITED
- Owner's Engineer in relation to the procurement and construction phase of an EPC contract for an expected 40â60 MW, run of river, hydro-electric power plant and associated facilities in Zambia · £240,000 · 18 Nov 2016
- Environmental and Social Advisory Services for a 50MW Wind Power Project in Ghana · £250,000 · 6 Oct 2016
- Environmental and Social Advisory Services for a 50MW Wind Power Project in Ghana · £250,000 · 3 Oct 2016
- Lake VIctoria Marine Transport Services Procurement of Commercial Services Provider · £164,176 · 8 Mar 2016
- Legal Services for Western Power Company Limited · 27 Jan 2016
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Supply of Electricity · St Helens College · £2,498,096
- Electricity supply · LEEDS TRINITY UNIVERSITY · £558,249
- Provision of Electricity Supply · NHS Blood and Transplant · £7,400,000
- Electric NHH · THE CAMBRIDGE HOUSING SOCIETY LIMITED · £370,871
- Bernicia - Electrical Works Programme · PROSPER
- Supply of Electricity · East Riding of Yorkshire Council · £80,800,000
- Supply of Electric and Bill Validation Services · Bassetlaw District Council · £2,245,239
- ESPH740 NB RDC Electricity UMS · Rother District Council · £39,455
source
Published on Contracts Finder. Contact details for named individuals are not reproduced on this site.