The value below is a framework or dynamic market ceiling: the maximum that could be spent across all call-offs, not the value of a single contract. Aggregate figures on this site exclude these to avoid double counting.

key details

Statuscomplete
RegionEast Midlands
Procedureselective
OCIDocds-h6vhtk-06cb87

Award

SupplierValueDateStatus
BREHENY CIVIL ENGINEERING LIMITED · · active

description

Yarborough Road

The project consists of the removal of the existing retaining walls and layby at the top of Whittons Park. This will then be replaced by a reinforced earth (plastic grids, imported fill) slope that ties into the park. The works will consist of the following disciplines, earthworks, drainage, surfacing, kerbing, footways, street lighting, lining, fencing and landscaping. The project has an agreed satellite compound at the base of the park to handle materials.

Ropewalk Gyratory

The project consists of the reconstruction/resurfacing of Ropewalk Gyratory outside Lincoln University from Brayford Wharf East to Centaur Road (Morrisons) to Brayford Way (McDonalds). As part of these works the signals will be refreshed by LCC with the civils elements such as new socket installation being undertaken as part of this contract. There will also be new kerb and footway works included in the package. The works will consist of the following disciplines, drainage, surfacing, kerbing, footways, street lighting and lining. It is expected that the main compound will be positioned on Beevor Street for both sites due to exiting hard standing being in place

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
15 Jul 2026 Contract details (UK7) Procurement Act 2023 066556-2026

more from Lincolnshire County Council

all contracts from this buyer →

source