Gaseous Hydrogen Pressure Reduction Station
key details
| Value | £35,000 (£42,000 inc. VAT) |
|---|---|
| Status | active |
| Category (CPV) | 38800000 |
| Deadline | 13 Mar 2026 |
| Procedure | open |
| OCID | ocds-h6vhtk-064efc |
description
HSE require a gaseous hydrogen pressure reduction station for use during a research test programme. The PRS will be connected to a bulk hydrogen supply up to 500 barg.
The PRS should be able to control a flow of gaseous hydrogen at a set flow rate within the range 20 - 400 g/s. The system should respond to a setpoint which is determined from an analogue signal sent to the pressure regulator.
If a dome regulator is used, HSE will provide and install a nitrogen supply to the regulator.
The PRS will be connected to a vent stack and pressure relief system, which will be provided and installed by HSE before the system is used for experiments.
The PRS should be instrumented with pressure and temperature upstream and downstream of the regulation, and a mass flow meter.
These sensors should have analogue outputs (ideally 4-20 mA signals) suitable for connection to a separate data logging system. Please give details of the accuracy and calibration of instrumentation. Instrumentation should be ATEX rated and suitable for hydrogen.
Inlet: Hydrogen @ up to 500 barg, -10 to 25 °C
Outlet: Hydrogen @ up to 100 barg, up to 400 g/s
Pipework: 1" ID stainless 316L steel, 1 connection suitable for 500 barg to tube trailer, 1" Class 900 flange on the downstream connection. Upstream of the regulator, the system should have a maximum allowable working pressure of at least 700 barg.
Downstream of the regulator, the system should have a maximum allowable working pressure of 150 barg and a bursting disc set for this pressure. The PRS should also include an upstream isolation valve with a maximum allowable working pressure of at least 700 barg. This valve should be pneumatically actuated and include an ex-d position indication.
Instrumentation: Pressure and temperature upstream and downstream of the regulator, mass flow meter after the regulator. Instrumentation should be ATEX rated, suitable for hydrogen. 4-20 mA output preferred. Please give details of the accuracy of instrumentation.
Skid: The pressure reduction system should be mounted on a skid with ports suitable for transport with a forklift. The skid must have attachment points for bolting to ground and points for earthing the system.
A Q&A drop in session regarding this tender will be held on 18/02/2026 at 13:00 GMT Please respond VIA In-Tend for invitation details
The equipment is required for use at the HSE Buxton (SK17 9JN) test site
documents
- https://www.find-tender.service.gov.uk/Notice/012868-2026 , tenderNotice
Documents are linked, not mirrored. They are served by the publishing authority and may require registration.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 12 Feb 2026 | Tender notice (UK4) | Procurement Act 2023 | 012868-2026 |
more from Health and Safety Executive
- The Provision of Media and Marketing for HSE · £2,000,000 · 28 Jul 2026
- The Provision of a Website Hosting Service · £748,000 · 15 Jul 2026
- The Provision of an External Lawyer to Draft a Statutory Instrument · 9 Jul 2026
- The Provision of External Support for the Discovering Safety Programme · 19 Jun 2026
- 8 m Hinged Lighting Columns · £14,000 · 10 Jun 2026
- THE PROVISION OF SPECIALIST TRAINERS TO SUPPORT HSE IN THE DELIVERY OF THEIR COMMERCIAL TRAINING AND EVENTS · £1,900,000 · 9 Jun 2026
- Post Occupancy Overheating Review of New Dwellings · 21 Apr 2026
- The Provision of Pressure Systems Consultancy Services · £48,000 · 16 Apr 2026
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Supply, Deployment, and Translation of Hydrophones for Underwater Acoustic Facility · NPL Management Limited · £200,000
- Sellafield PLC- DAMS Offline Feasibility Rig · Sellafield ltd · £184,741
- MSSS (Magnox Swarf Storage Silo) Plant Control System Offline Feasibility Rig · Sellafield Limited
- XY Punch · United Kingdom National Nuclear Laboratory · £2,500,000
- Supply of Temperature Control System - AWARD · CPI (Centre for Process Innovation)
- GB-Swindon: UKRI-3641 Provision of Master Slave Manipulators · UK Research and Innovation, Science and Technology Facilities Council · £178,170
- 2359a - NIBF2 Chiller Unit · Centre for Process Innovation Limited · £177,898
- 22/SJM/075 Automation Engineering Robots, Sensors, Controls, Manufacturing · Univesity of Portsmouth · £800,000
source
Published on Find a Tender. Contact details for named individuals are not reproduced on this site.