UKNNL is seeking expressions of interest from suitably qualified and experienced contractors to support the assembly, installation verification, and inactive commissioning of a new modular experimental rig at the Preston facility.

The rig comprises a modular, three-storey structure incorporating multiple process and utility services. The appointed contractor will be responsible for mechanical assembly, installation checks, and inactive commissioning (without uranics) to enable active commissioning (with uranics) by others.

  1. Scope of Work

The contractor will be expected to undertake, as a minimum:

Mechanical Assembly

Offloading, positioning, and installation of prefabricated rig modules
Mechanical assembly and integration of modules to form the complete structure
Installation of access platforms, supports, and ancillary equipment
Alignment, fixing, and structural integrity checks

Interface & Service Readiness

Preparation and verification of interfaces for:
oGas services
oExtraction/ventilation
oFluids
oElectrical supplies
Coordination with service installation contractors
Ensuring connection points are accessible, correctly labelled, and compliant with drawings/specifications

Electrical, Controls and Instrumentation:

Cross module connections
Final install
Connection to Pilot Plant electrical distribution network
  1. Project Overview

UKNNL is seeking expressions of interest from suitably qualified and experienced contractors to support the assembly, installation verification, and inactive commissioning of a new modular experimental rig at the Preston facility.

The rig comprises a modular, three-storey structure incorporating multiple process and utility services. The appointed contractor will be responsible for mechanical assembly, installation checks, and inactive commissioning (without uranics) to enable active commissioning (with uranics) by others. ________________________________________

  1. Scope of Work

The contractor will be expected to undertake, as a minimum:

Mechanical Assembly

Offloading, positioning, and installation of prefabricated rig modules
Mechanical assembly and integration of modules to form the complete structure
Installation of access platforms, supports, and ancillary equipment
Alignment, fixing, and structural integrity checks

Interface & Service Readiness

Preparation and verification of interfaces for:
oGas services
oExtraction/ventilation
oFluids
oElectrical supplies
Coordination with service installation contractors
Ensuring connection points are accessible, correctly labelled, and compliant with drawings/specifications

Electrical, Controls and Instrumentation:

Cross module connections
Final install
Connection to Pilot Plant electrical distribution network

Installation Verification

Completion of installation checks against drawings and specifications
QA/QC inspections and documentation
Identification and resolution of defects or non-conformances
As-built documentation and redlining

Inactive Commissioning

Mechanical completion checks
Pressure/leak testing (where applicable)
Functional checks (non-energised / non-process)
Safety and compliance verification
Handover documentation and commissioning packs

________________________________________

  1. Contractor Requirements

Interested parties should demonstrate:

Experience assembling modular or multi-storey industrial/process rigs or plant
Experience working with multi-disciplinary service interfaces (gas, fluids, extraction, electrical)
Commissioning and mechanical completion experience
Strong health, safety, and quality management systems to comply with CDM regulations
Ability to work within an operational facility environment
Relevant certifications and competencies

________________________________________

  1. Deliverables

The appointed contractor will be expected to provide:

Method statements and risk assessments
Installation and commissioning plans
Inspection and test records
Mechanical completion dossiers
As-built documentation
Handover pack

________________________________________

  1. Programme (Indicative)
Site readiness: June 2026
Assembly period: 3 months
Handover to active commissioning: September 2026

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
9 Feb 2026 Preliminary market engagement (UK2) Procurement Act 2023 011320-2026

more from UNITED KINGDOM NATIONAL NUCLEAR LABORATORY LIMITED

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Find a Tender. Contact details for named individuals are not reproduced on this site.