Toilets
key details
| Status | complete |
|---|---|
| OCID | ocds-h6vhtk-05e214 |
Award
| Supplier | Value | Date | Status |
|---|---|---|---|
| Internal Projects Limited | · | · | active |
description
The works include the full strip-out, refurbishment, and reinstallation of sanitary fittings, finishes, and associated building and plumbing works to the existing toilet area.
- 1.Strip Out and Preparation
- a.Strip out and remove existing toilet, sink, and associated fittings.
- b.Carry out full demolition/soft strip of redundant fixtures, finishes, and
pipework as required.
- c.Remove existing internal door and door furniture.
- d.Dispose of all waste materials in accordance with site waste management and environmental regulations.
- e.Make good all disturbed areas to a sound and even finish ready for decoration.
- 2.Windows
- a.Make good 2 no. existing windows, including repair of frames, cleaning, sealing, and preparation for decoration as required.
- 3.Decoration
- a.Prepare all wall, ceiling, and wood surfaces.
- b.Apply one mist coat and one full coat of quality trade emulsion to walls and ceilings.
- c.Apply suitable finish paint to all woodwork, trims, and window frames.
- 4.Joinery Works
- a.Refurbish existing door, including sanding, filling, repainting/staining, and fitting new door furniture (handle, lock, and signage).
- b.Install shelving to support new water heater - securely fixed, level, and able to support full load of the appliance.
- c.Construct and install heater cover (removable for access and maintenance), finished to match surrounding décor.
- d.Carry out any required boxing-in of pipework to provide a neat and accessible finish.
- 5.Plumbing Works
- a.Supply and install new close-coupled WC suite, including pan, cistern, seat, and all fixings.
- b.Supply and install new sink with thermostatic mixing tap.
- c.Supply and install new 15-litre electric water heater.
- d.Complete all associated pipework, waste, and lagging to meet current Building and Water Regulations.
- e.Pressure test system upon completion.
- 6.Mechanical Works
- a.Core hole through external wall for new extract fan installation (fan to be supplied separately or as specified).
- b.Seal all penetrations weather-tight and make good finishes.
- 7.Completion
- a.Ensure all works are clean, fully operational, and tested.
- b.Remove all rubbish and debris from site.
- c.Provide user instructions for all new equipment (heater, tap, etc.).
- d.Leave area ready for immediate use
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 17 Nov 2025 | Contract details (UK7) | Procurement Act 2023 | 074228-2025 |
more from North East London NHS Foundation Trust
- Splashtop Enterprise Support Licences · 17 Jul 2026
- Sofas for Ward · 10 Jul 2026
- Roof Replacement · 10 Jul 2026
- NELFT - Outsourced Clinical Transcription RFI · 3 Jun 2026
- NELFT Voluntary & Community Sector (VCS) Peer Worker Provision · £664,000 · 29 May 2026
- Medical Couches · 29 May 2026
- Fire Doors · 29 May 2026
- Recruitment · 22 May 2026
all contracts from this buyer →
source
Published on Find a Tender. Contact details for named individuals are not reproduced on this site.