Controls and BMS package to enable the operation and monitoring of the CHP LTHW heat recovery system

THE PIRBRIGHT INSTITUTE Published 24 Jun 2025 Find a Tender

key details

Statuscomplete
RegionSouth East
Proceduredirect
OCIDocds-h6vhtk-054dfb

Award

SupplierValueDateStatus
SCHNEIDER ELECTRIC LIMITED · · active

description

The CHP LTHW Heat Recovery Project is to enable heat generated from the CHP as low temperature hot water to offset steam production used for heating and hot water within the Plowright building. Utilising the available LTHW provides a significant energy saving and delivers maximum efficiency from the CHP that operates onsite.

Existing controls and BMS operate on the Schneider Electric platform. For continuity and standardisation, it is required that the controls and BMS package to operate and monitor the heat recovery system is via the existing Schneider system.

notice history

2 notices published against this procurement.

PublishedTypeRegimeNotice
17 Jun 2025 Contract details (UK7) Procurement Act 2023 032836-2025
24 Jun 2025 Contract change (UK10) Procurement Act 2023 034803-2025