Teddington Direct River Abstraction (TDRA) Tunnelling Main Works Contract (MWC)

THAMES WATER UTILITIES LIMITED Published 28 May 2025 Find a Tender

key details

Statusactive
Category (CPV) 45000000
RegionLondon
Procedureselective
OCIDocds-h6vhtk-05286c

description

Design, build, test and commission of the following two main components:

i)A recycled water conveyance tunnel from Mogden Sewage Treatment Works (STW) to Teddington. A new approximately 4.2km long tunnelled conveyance route approximately 3.5m internal diameter (ID) would be driven using a Tunnel Boring Machine (TBM) and constructed to connect a new Tertiary Treatment Plant (provided by others) in Mogden STW to the proposed outfall on the riverbank of the River Thames upstream of Teddington Weir. The tunnel would have four shafts.
ii)River abstraction and transfer to the existing Thames Lee Tunnel (TLT): The river abstraction would be located approximately 175m upstream of the proposed new outfall. The abstracted river flow would be conveyed to the TLT through a smaller diameter (up to 2.2m ID) pipe installed using a pipe jacking technique.

The scope will include, but not be limited to:

Construction Design activities

Architectural

Building M&E

Civils and Structural engineering including earthworks

Enabling works

Drainage

Geotechnical

Ground movement impact

Mechanical, Electrical, Instrumentation, Control and Automation (MEICA) including a SCADA (Supervisory Control and Data Acquisition) system

Hydraulic Modelling

Materials durability

Renewables / Carbon mitigation

Rivers and Watercourses

Traffic & Highways

Shafts & Tunnels

Utilities

Disposal of excavated material

The NEC4 Engineering and Construction Contract comprise two stages, with a decision point as to whether to proceed to construction between Stages One and Two. If the decision point is passed, then a Notice to Proceed (NTP) will be issued.

Stage One, also known as the Early Contractor Involvement stage, will provide construction related support to the Client during its planning process, which comprises an application for a Development Consent Order (DCO). Using the DCO reference design (provided by others) as a constraint to the scope, the TDRA Tunnelling MWC will develop the design for construction, which will be integrated with construction planning, into the subsequent Stage Two, being the delivery / construction phase.

The decision gate to proceed to Stage Two will be dependent on a number of matters, including: 1) An accepted design that meets the requirements of the contract; 2) agreement on a target price; and 3) the granting of the DCO. The agreement of a target price for Stage Two will be constrained by the Client's budget and will be developed in accordance with a Pricing Information Schedule appended to the contract. The Pricing Information Schedule will include an exhaustive list of specific "Adjustment Events" which may adjust the target price for Stage Two.

Subject to the Client issuing a NTP, Stage Two will commence with an initial period to comply with any secondary consenting issues, followed by mobilisation to commence construction. Following construction, a testing and commissioning phase will be required with a scheduled target date of Water Available for Use (WAFU) of 31 March 2033.

documents

Documents are linked, not mirrored. They are served by the publishing authority and may require registration.

notice history

1 notice published against this procurement.

PublishedTypeRegimeNotice
28 May 2025 Tender notice (UK4) Procurement Act 2023 028281-2025

more from THAMES WATER UTILITIES LIMITED

all contracts from this buyer →

similar contracts awarded

Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.

source

Published on Find a Tender. Contact details for named individuals are not reproduced on this site.