Barbican Podium Waterproofing, Drainage and Landscaping Works (Ben Jonson, Breton & Cromwell Highwalk) Phase 2 – 1st Priority Zone
key details
| Value | £12,500,000 |
|---|---|
| Status | planned |
| Category (CPV) | 45200000 +1 more |
| Region | London |
| OCID | ocds-h6vhtk-03b1c1 |
description
- Project Description
The Barbican Estate is grade 2 listed with a multitude of uses including an arts centre, 2014 dwellings, exhibition halls, cinemas, restaurants theatres, gallery space and a large conservatory. Designed and constructed in the 1960s and 1970s by architects Chamberlin, Powell and Bon the Barbican Estate represents a prominent example of brutalist architecture. The publicly accessible podium provides a pedestrian only elevated walkway connecting the residential towers, terraces and the Barbican Centre. The existing podium is predominantly made up of brick tiles with areas of defined planting set within the podium.
The existing podium deck and waterproofing membrane has become damaged and is leaking into the buildings below including the Exhibition Halls.
The City of London, as the owner and manager of the estate, is currently undertaking a large-scale refurbishment of the podium deck. Phase 1 of this refurbishment was completed in 2015, this project will focus on Phase 2; a 18,344sqm area along the northern portion of the estate. Several more phases are expected to be required in order to repair other parts of the podium. An initial feasibility study was undertaken that demonstrated several reasons for this including:
- the drainage system;
- damage to the waterproofing;
- shallow crossfalls;
- detailing of the expansion joints.
The podium deck needs be taken up to replace and repair the damaged waterproofing membrane. Works were completed on phase 1 in 2015. This project builds on the lessons learned from phase 1 for the area identified as phase 2.
Surface refurbishment, replacement of waterproofing membrane, remedial works to drainage infrastructure, and landscaping works to Barbican Podium Phase 2, 1st Priority Zone.
notice history
1 notice published against this procurement.
| Published | Type | Regime | Notice |
|---|---|---|---|
| 10 Mar 2023 | Prior information notice (F01) | Earlier regulations | 007036-2023 |
more from The City of London Corporation
- Dispute Resolution Consultant for Sydenham Hill Project · £30,000 · 20 Jan 2026
- Guildhall Chilling/Humidification Plant Replacement · £97,884 · 3 Dec 2025
- Legal Advisory Services in Relation to the Barbican Renewal Project · £77,910 · 28 Oct 2025
- Common Data Environment for the Barbican Renewal Programme · £50,900 · 8 Jul 2025
- Pan London Homeless Substance Misuse Programme – Combined In Patient Detoxification Unit for London · 11 Mar 2025
- Pest Control Provision for Housing Estates · £63,000 · 27 Feb 2025
- Comms Consultancy · £88,590 · 26 Feb 2025
- Barbican Lucy Raven Exhibition · £108,580 · 26 Feb 2025
all contracts from this buyer →
similar contracts awarded
Other awarded contracts in the same category. Useful for seeing who normally wins this kind of work, and at what value.
- Pickering Road Concrete Repairs · Hull City Council · £59,171
- COV-Cycle Routes · Coventry City Council · £3,400,000
- Day Works Civils · VIA EAST MIDLANDS LIMITED · £4,000,000
- SVRP Civils & Marine Works Framework · Caledonian Maritime Assets Ltd (Utility)
- SVRP Civils & Marine Works Framework · Caledonian Maritime Assets Ltd (Utility) · £15,600,000
- Highways Structures Programme · Cheshire west and Chester Borough Council · £21,000,000
- Conversion of a former Bank to Library Hub · Launceston Town Council
- Newry, Mourne & Down District Council Civil Engineering Minor Works Framework Agreement 2025-2029 · Newry Mourne & Down District Council
source
Published on Find a Tender. Contact details for named individuals are not reproduced on this site.